CONSTRUCTION CLAIMS UNDER GEORGIA LAW
Introduction to Construction Claims
Georgia courts recognize a wide variety of claims which are of importance
to contractors. By its very nature, the construction industry is contentious
and filled with a wide variety of claims and disputes. Even the best-managed
project is likely to have one or more significant disputes which may imperil
the successful completion of the project.
In this hostile and competitive environment it is critical to know and
understand your rights and obligations under Georgia law. This manual is
intended to assist general contractors, subcontractors, owners, design
professionals, material suppliers, and others who deal with the difficult
problems encountered in the construction industry in Georgia. The materials
assume a working knowledge of construction industry practice and methods.
1. General Principles of Contract Interpretation
All contracts are subject to certain rules of construction which are
used by the courts to interpret and enforce the contract.
Contracts can be either written or oral. Both are enforceable, although
the law requires that certain contracts be made only in writing. These
include real estate sales contracts, contracts of suretyship, and certain
other contracts.
A court ordinarily will enforce the meaning and intention of the parties
as reflected by the contract. Parties laboring under no disabilities (illiteracy,
blindness, etc.) may make contracts on their own terms, and in the absence
of fraud or mistake or terms that are illegal or contrary to public policy,
they must abide by that contract. The fact that the contract is unwise
or disadvantageous to one of the parties is no reason for disregarding
it. Yon v. City of Atlanta, 201 Ga. 800, 41 S.E.2d 516 (1947).
For example, if the parties to a contract enter into an express agreement
setting out a pricing formula for extra work, then that contract will be
enforced, even if it later appears that the contractor cannot properly
document its direct costs as required by the contract. Gilbert v. Powell,
165 Ga. App. 504, 301 S.E.2d 683 (1983); Foster v. Waverly Hall United
Development Corp., 159 Ga. App. 710, 285 S.E.2d 35 (1981)(failure to
keep proper records may waive mechanic's lien).
Where a contract sets up reasonable conditions precendent to a claim
or defense, the opposite party usually may assert the failure to comply
with these conditions as a defense. But the courts also exist to do justice,
and it has been stated that "the courts will readily seize upon circumstances
arising in the subsequent conduct or transactions of the parties and imply
a waiver, in order to prevent a forfeiture because of non-compliance with
formal prerequisites.
Biltmore Construction Co. v. Tri-State &c.,
Inc., 137 Ga. App. 504, 224 S.E.2d 487 (1976).
The court may intervene to prohibit the enforcement of illegal contracts,
and under certain limited circumstances the court will exercise its equitable
powers to prevent an injustice from occurring, but these exceptions to
enforcement of the plain meaning of the contract are rare.
Where the court determines that the meaning and intention of the parties
is ambiguous, the court must apply certain rules of construction in order
to resolve the ambiguity. O.C.G.A. § 13-2-2.
For example, the courts will ordinarily construe the contract against
the party who drafted the contract. This means that if the contract is
subject to more than one reasonable interpretation, all other things being
equal the courts will favor the interpretation of the party who did not
draft the contract. O.C.G.A. § 13-2-2(5).
Likewise, those provisions added by the parties will control over conflicting
provisions in a pre-printed form. Batson-Cook v. Poteat, 147 Ga.
App. 506, 249 S.E.2d 319 (1978)(applying O.C.G.A. § 13-2-2(7)).
The court has the duty to construe and enforce the meaning and intention
of the parties as expressed in a written contract. If the court determines
that there is an ambiguity in the contract, which the court cannot resolve
after applying these rules of construction, then court must submit the
issue of the meaning and intention of the parties to the jury for a factual
determination. Travelers Insurance Co. v. Blakey, 180 Ga. App. 520,
349 S.E.2d 474 (1986).
Where a contract has been reduced to writing, the courts generally will
not consider "parol evidence" (i.e., oral or verbal testimony) which
attempts to contradict or vary the terms of a valid written agreement.
O.C.G.A. § 24-6-1.
Parol evidence is admissible to explain all ambiguities in writings.
O.C.G.A. § 24-6-3. Fruin-Colnon Corp. v. Air Door, Inc., 157
Ga. App. 804, 278 S.E.2d 708 (1981)(reversing trial court's exclusion of
such evidence introduced to explain an ambiguity).
CLAIMS ADMINISTRATION
2. Maintaining Claim Records
The most important part of claims administration is keeping good records.
Most project administrators think that they keep good records, but surprisingly,
most do not consider the fact that others will be reading these records
later and attempting to reconstruct what actually occurred on the project,
when it happened, who saw it happen, and explaining why it happened. The
absence of records also can be a critical problem, since it leads to the
inference that the claim event may have occurred due to different causes,
at a different time, or perhaps may never have occurred at all.
As an evidentiary matter, contemporaneous project records also are important
because in order to introduce the records in court, the proponent of the
records must be prepared to show that the records were "business records"
kept in the ordinary course of business and were relied upon in the operation
of the business. If these facts cannot be proven, then the records are
of limited value as evidence in a construction trial.
The contractor should designate at least one person to keep detailed
records as the project is built. These records should be reliable and accurate
records of the actual events which occurred on the job. Records which should
be kept include bid documents, correspondence (particularly notices and
change order correspondence), schedule impacts (weather records, late deliveries,
equipment problems, etc.), contracts and change orders (including requests
for change orders not approved), a daily job diary, weekly reports, scheduling
records (CPM, bar charts, etc.), minutes of job meetings (tapes are good
records to back up written minutes), cost records (invoices, billings,
hourly labor records including labor burden), applications for payment,
cancelled checks, design and shop drawings, equipment utilization reports,
job cost and other accounting reports.
Some of the most important records for the contractor or subcontractor
are estimate and bid preparation records. These records show what the contractor
expected to expend in constructing the project and permit a quick review
of where costs differed from those projected at the start of the project.
Most contractors keep their original estimate, but often do not use
these records to track progress on the job. It is particularly useful for
the contractor to know which job costs or units were above or below originally
estimated quantities. Such records help to validate the bid and also provide
the contractor with an early warning of problems.
Retaining estimates and bid records also help to prove that any cost
overruns encountered on the project were not caused by bid errors or a
bad estimate. As discussed in more detail later, the contractor's original
estimate also can be used to prepare a "total cost" or "revised total cost"
claims. In the absence of more complete records, a comparison of the contractor's
"as planned" versus "as built" costs through the use of the original estimate
and final job costs may be the only way the contractor can price a claim.
Every project manager recognizes the importance of project correspondence,
transmittals, and notices. These records provide vital evidence of what
occurred on the job and when. It is very helpful to instruct the project
secretary to stamp all mail or transmittals with the date the document
was received. Often, correspondence is actually received many days after
the date on the letter or transmittal, and the only way to prove this later
is with a date stamp showing when the document actually was received.
Drawings and submittals also can be critical elements of a successful
claim. It is surprising how casually contractors treat construction drawings
which may be the only record of design changes or errors, or which may
provide crucial support for a contractor's claim of extra work. A "record
set" of drawings stamped with the date of receipt and kept in chronological
order is extremely helpful in reconstructing the design development of
the project. If drawings are lost, damaged or become illegible then it
may be very difficult to prove later exactly what the contractor was being
asked to build.
Shop drawings also are extremely important records. Often, the contractor
is required by contract to describe exactly how the work is to be installed.
The approval stamp on the drawings by the architect or engineer can provide
crucial evidence that the contractor's means and methods of construction
were known to the owner's design professionals.
Shop drawings can be very important evidence of adverse impact on construction
progress due to design changes or owner interference. They are important
evidence of how the contractor intended to construct the project. Dates
on the review stamps also can establish delay in approval or transmittal
of shop drawings which may result in construction delays.
Construction specifications, including a complete set of all revisions
to the specifications, should be retained and filed in chronological order.
It also is helpful to keep a marked up master set of specifications showing
exactly how any revisions to the specifications modified the original specifications.
It is surprising how often construction claims relate in some manner
to revisions in project specifications which were not communicated or acted
upon by subcontractors and suppliers. Accordingly, it is very important
to retain transmittals reflecting the dates when revised specifications
were sent or received.
Submittals and cut sheets can provide detailed product information,
including product interaction, tolerances, materials properties, safety
and other important data. Comparison of submittals to "as built" conditions
can prove whether the product or materials meet the requirements of the
contract. If a product fails, cut sheets can help to prove any express
or implied warranties of the product.
Daily and weekly reports are critical job records. Ideally, these reports should be an accurate and complete record of who was on the job, what they were doing, and any impacts on the progress of their work by others. These records often are transmitted to others, and if they are they can be used to establish written notice of facts or job condition as of a date certain. The accurancy and completeness of daily and weekly reports is often the critical element in the success or failure of a delay claim. It should go without saying that the daily and weekly reports are no place for the project manager or superintendent's personal appointments and notes.
3. Notices & Protests
.1 General Principles
Giving notice of the contractor's position is often the critical determining
factor in determining whether the claim will succeed or fail. Absent some
affirmative action creating waiver or estoppel, where the contract makes
notice a condition precedent to recovery of a claim, the failure to give
notice bars a contract claim. State Highway Department v. Hewitt Contracting
Company, 113 Ga. App. 685, 149 S.E.2d 499 (1966).
Where the parties enter into a contract providing for liquidated damages
for delay, but the contractor fails to follow the requirements of the contract
and timely apply to the owner for an extension of time for delays beyond
its control, and the contractor produces no other evidence of a contractual
defense, then the contractor loses its right to a time extension under
the contract and the owner may recover liquidated damages from the contractor
as matter of law. Dan-D, Inc. v. Burnsed Enterprises, Inc., 188
Ga. App. 207, 372 S.E.2d 303 (1988).
Where a contract requires that the contractor notify the owner of any
claims for extra work or extra cost by the presentation of a claim with
the first estimate filed after the changed or extra work was performed,
and the contractor fails to follow this requirement of the contract, the
contractor was not entitled to recover for its additional work. Goodwin,
Inc. v. City of Lafayette, 418 F.2d 698 (5th Cir. 1969)(finding the
conduct of contractor in waiting two years after completion of project
to submit claim "does not add up to open and fair dealings").
In any event, it always is the better practice to notify a supplier
or subcontractor of a claim of defective performance or defective materials
prior to initiating any repair which may result in a backcharge. Whether
it is reasonable and customary to backcharge a supplier for the cost to
repair a defective product without prior notice to the supplier is a question
of fact to be submitted to the fact finder for a determination. Fruin-Colnon
Corp. v. Air Door, Inc., 157 Ga. App. 804, 278 S.E.2d 708 (1981).
If the owner or its agent directs the contractor to perform some action
to which the contractor objects or believes is a violation of the contract,
then the contractor should indicate its position by sending a notice that
it is performing under protest. Simply notifying the opposite party of
price escalations or extra handling charges without acceptance of those
charges by the opposite party does not assure collection of those charges.
See
Fruin-Colnon Corp. v. Air Door, Inc., 157 Ga. App. 804, 278 S.E.2d
708 (1981).
If the owner disagrees with the position taken by the contractor in
the notice of protest, the owner should tell this to the contractor. The
notice of protest may be considered by a court to be a counteroffer by
the contractor. The owner's silence may be considered to be an acceptance
of the counteroffer and may result in the owner being deemed to have waived
contract conditions which conflict with the contractor's position, or to
have accepted the contractor's work subject to the conditions set out in
the notice of protest. State Highway Department v. Wright Contracting
Co., 107 Ga. App. 758, 131 S.E.2d 808 (1963).
Where the opposite party is placed on notice that work is considered
to be extra, the failure to follow the requirements of the contract for
pricing and advance written approval of the extra work were not fatal to
the claim. Batson-Cook Company v. Loden & Company, Inc., 129
Ga. App. 376, 199 S.E.2d 591 (1973).
Provisions as to notice must be reasonably construed. State Highway
Department v. Hall Paving Co., 127 Ga. App. 625, 194 S.E.2d 493 (1972).
.2 Mutual Departure from Notice Requirements
Where a general contractor requires a subcontractor to perform extra
work outside the foreseeable scope of its contract, with actual notice
of the extra expenses which are being incurred by the subcontractor, then
the general contractor may be found to have taken the subcontractor's claim
for this extra work outside the scope of the notice requirements of the
original contract. Ballenger Corporation v. Dresco Mechanical Contractors,
Inc., 156 Ga. App. 425, 274 S.E.2d 786 (1980).
.3 Notice Required Under Uniform Commercial Code
Where the claim is made for a defect in a product which is regulated
by the Uniform Commercial Code, notice of the defect must be given to the
seller of the goods. The notice must be within a reasonable time after
the buyer discovers or should have discovered the defect.
The failure to give the statutorily required notice bars any remedy
under the UCC. O.C.G.A. § 11-2-607(3)(a). Fruin-Colnon Corp. v,
Air Door, Inc., 157 Ga. App. 804, 278 S.E.2d 708 (1981).
The UCC expressly permits the buyer to backcharge the seller for any
damages sustained from the breach. The UCC requires that this is done by
notifying the seller that the buyer is deducting all or any part of the
damages resulting from the breach of contract from any part of the price
still due under the contract, pursuant to O.C.G.A. § 11-2-717.
4. Securing Claim Information
.1 Georgia Open Records Act (O.C.G.A. § 50-18-70)
The Georgia Open Records Act, O.C.G.A. § 50-18-70, provides that
public records such as documents, papers, letters, maps, books, tapes,
photographs, or similar material perpared and maintained by a state agency
are open for inspection by any citizen of the state at a reasonable time
and place.
Photographs or reproductions of these records are permitted, with reasonable
fees for copies made by the government. O.C.G.A. § 50-18-71.
Certain state records exempt from production. O.C.G.A. § 50-18-72.
Where access is refused without substantial justification, a party may
collect reasonable attorneys' fees and costs incurred in bringing an action
to compel access to these records. O.C.G.A. § 50-18-73.
.2 Freedom of Information Act
The Freedom of Information Act, 5 U.S.C. § 552, requires the federal
government to provide information and records maintained by the federal
government, including administrative information which might not be readily
accessable through other means. Each agency promulgates regulations which
control how this information is to be requested and the fees associated
with a request.
.3 Obtaining Copies of Contracts and Bonds
At the beginning of any construction project it is preferable for potential
claimants to obtain copies of any labor and material payment bonds posted
by the general contractor. It is much easier to obtain copies of the bonds
before a dispute arises.
The Miller Act provides that the department secretary agency head of
the contracting agency is authorized and directed to furnish to any person
making application therefor who submits an affidavit that he has supplied
labor and materials for such work and payment therefor has not been made
or that he is being sued on any such bond, a certified copy of such bond
and the contract for which it is given, which copy shall be prima facie
evidence of the contents, execution and delivery of the originals. A fee
must be paid for these copies. 40 U.S.C. § 270c.
Georgia's Little Miller Act provides that a copy of the bond issued
on any public project may be secured from the officer who has custody of
the bond. To obtain the bond, an applicant must submit an affidavit. The
affidavit must state that the claimant (1) has supplied labor or materials
for which work and that payment therefore has not been made; or (2) that
he is being sued on any such bond or security deposit. Upon receipt of
such an affidavit, the officer having custody of the bond must give a copy
of the bond and the contract for which it is given, certified by an that
official. O.C.G.A. § 36-82-104(e).
A certified copy of the bond obtained under this section is prima facie evidence of the existence and terms of the bond. Western Casualty & Surety Company v. Fulton Supply Company, 60 Ga. App. 710, 4 S.E.2d 690 (1939). It is not necessary to obtain a certified copy in order to sue on the bond. So. Surety Company v. Dawes, 161 Ga. 207, 130 S.E. 577 (1925).
5. Flow-Down Clauses
A flow-down clause is a contract provision which creates an obligation
in a "downstream" party to comply with or be bound by some obligation of
the "upstream" party, usually in the same manner or in the same degree
as the upstream party is bound. For example, a flow-down clause may say
that the downstream party must arbitrate if the unsteam party is served
with a demand for arbitration.
Flow-down clauses also commonly obligate each subcontractor to comply
with all of the obligations which are assumed by the general contractor
in its contract with the owner. In such cases it is extremely important
for the subcontractor to ask for a copy of the general contractor's contract
with the owner and to carefully review it. If this is not done, then the
subcontractor may inadvertently fail to comply with some condition of the
general contractor's contract with the owner, perhaps leading to an inadvertent
waiver of the subcontractor's claim.
Flow down provisions usually are treated by the courts as constituting
"incorporating by reference" the provisions involved. Such clauses are
effective where the provision to which reference is made has a reasonable
clear and ascertainable meaning. Binswanger v. Beers, Inc., 141
Ga. App. 715, 234 S.E.2d 363 (1977); Arthur Pew Construction Co., Inc.
v. Bryan Construction Co., Inc., 148 Ga. App. 114, 251 S.E.2d 105 (1978)(incorporating
an indemnity clause).
Provisions incorporated by reference may not be effective to limit the
rights of a subcontractor where they are in conflict with other provisions
of the subcontract. Centex-Rodgers Construction Co. v. McCann Steel
Co., 206 Ga. App. 827, 426 S.E.2d 596 (1992).
6. Pass-Through/Liquidating Agreements
Claims are sometimes settled by the use of "pass-through" or "liquidating"
agreements. Often, these agreements permit a subcontractor to assert a
claim in the name of the general contractor against the owner, or require
the general contractor to assert claims on behalf of a subcontractor, or
assign contract rights or causes of action. In exchange for the agreement
to prosecute the claim, the subcontractor usually agrees to accept whatever
is recovered by the general contractor in satisfaction of the claim.
The legal basis for these agreements has been challenged where the pass-through
agreement makes it uncertain whether the general contractor is actually
responsible to the subcontractor for the damages asserted in the pass-through
claim. It is not sufficient for a general contractor to show that its subcontractor
has sustained damage without going further and showing that the general
contractor has some responsibility to the subcontractor for those damages.
Department
of Transportation v. Claussen Paving Co., 246 Ga. 807, 273 S.E.2d 161
(1980).
This is to be distinguished from pass-through agreements where the general contractor's obligation to pay the recovery on the claim to the subcontractor is made clear. In such cases the pass-though claim may be properly asserted by the general contractor on behalf of the subcontractor. Raymer v. Foster & Cooper, Inc., 195 Ga. App. 200, 393 S.E.2d 49 (1990).
BID CLAIMS
7. Bid Mistakes
Bid mistakes are a common problem. The "mistake" can take many forms.
"Unilateral" mistakes of fact include mistakes such as mathematical or
clerical errors, omission of bid items, erroneous assumptions, factual
misunderstandings or misinterpretations. Where a bid error of this type
occurs, contractors are often given relief from their bid mistake.
Other types of unilateral mistakes go to the judgment of the contractor in submitting its bid. These mistakes include erroneous estimates of the time to complete the project or the crews or equipment needed.
Likewise, unilateral mistakes caused by mere ignorance of the facts or of the legal or statutory requirements of the contract, normally do not form the basis for legal relief. In the absence of fraud, artifice, or deception, it is difficult to secure relief for these types of mistakes in Georgia. O.C.G.A. §§ 23-2-27, 23-2-29. In the absence of fraud, misplaced confidence, or some other misrepresentation, if a contractor though the exercise of reasonable diligence could have determined the true facts then equitable relief is not available. O.C.G.A. § 23-2-29.
In Georgia, mutual ignorance of fact (i.e., lack of knowledge
of some fact) does not afford a basis for equitable relief from
the contract. See O.C.G.A. § 23-2-28. Mutual ignorance of fact
is not considered the equivalent of a mutual
mistake of fact under
Georgia law.
Contractors often ask courts to modify or "reform" their bids to correct the bid mistake. If permitted, the relief will be granted only if the correction of the error does not affect the relative standing of the other bidders.
Most often, the reformation of the bid results from negotiation with
the owner rather than legal action, and the owner may condition the relief
upon waiving profit on the affected portion of the bid, or other concessions
by the contractor. Reformation is available in Georgia only in cases of
mutual mistake. O.C.G.A. § 23-2-31.
The remedy of cancellation or "recission" of the contract is available
for unilateral mistakes. See O.C.G.A. § 23-2-31. Recission
is often used where the owner caused the bid error, or knew or should have
known of the error. This may be the only viable remedy where the bid error
raises the contract price above the next lowest bidder.
It is much easier for the contractor to withdraw a bid, particularly
if the bid is withdrawn before the award of the contract. Bid withdrawals
are usually permitted for either unilateral or mutual bid mistakes, and
usually do not result in the forfeiture of the contractor's bid bond. The
sooner the contractor notifies the owner of the mistake, the easier it
is to obtain relief. Under Georgia law, relief from mistakes of fact may
only be obtained if the complaining party applies for relief within a reasonable
time. O.C.G.A. § 23-2-24.
Delay also increases the likelihood that the owner will rely on the
bid or take some action which would actually cause damage the owner. Kurfees
v. Davis, 178 Ga. 429, 173 S.E. 157 (1934)(relief from bid available
only where the bidder exercised ordinary diligence in discovering the truth
and the relief requested will not prejudicially affect the rights of others).
Even if the contractor was negligent or violated some legal duty in
making the mistake, relief still may be granted from the mistake if the
owner has not been prejudiced by the negligence. O.C.G.A. § 23-2-32.
As soon as a bid mistake is discovered, the contractor should immediately
notify the owner of the bid mistake, withdraw the bid, and cancel the bid
bond. This should be done first by telephone, and then confirmed in writing
by a telegram, fax, or hand-delivered letter. It is ideal if the date and
time that the notice was given is confirmed in writing, perhaps by an acknowledgement
of receipt of the notice by the owner or his representative.
A number of factors are often considered by the courts in granting relief
from a bid mistake. These include whether the mistake relates to a material
part of the contract (such as price), whether the mistake was caused by
gross negligence or violation of the law (courts are more likely to correct
"honest mistakes"), whether relief from the bid will cause the owner serious
prejudice (rebidding the contract, increasing the cost of the work, etc.),
and whether the mistake is so grave that to enforce the bid would be "unconscionable."
It usually is much easier for the contractor to ask a court to withdraw a bid. For example, in Peerless Casualty Co. v. Housing Authority, 228 F.2d 376 (5th Cir. 1955), the court held that where there is some reasonable excuse for an error in calculating the bid, and the party receiving the bid knows of the mistake at the time the bid is accepted, then the contractor may withdraw the bid. See First Baptist Church of Moultrie v. Barber Contracting Co., 189 Ga. App. 804, 377 S.E.2d 717 (1989)(general contractor permitted to withdraw bid for material mistake when owner notified prior to award, despite admitted negligence and 35-day acceptance period); State Highway Dept. v. MacDougald Construction Co., 54 Ga. App. 310, 187 S.E. 734 (1936) (withdrawal of bid permitted because delivery of bid and check were not supported by valuable consideration and thus the bid is merely a proposal and not a binding "option"; it therefore may be withdrawn before it is accepted and bidder may recover its deposit).
Normally, subcontractors and suppliers are not permitted to withdraw
their bids after they are submitted to the general contractor and relied
upon by the general contractor in submitting its own bid to the owner.
A fairly typical case where a subcontractor or supplier tries to withdraw
its bid is Frazier Associates Manufacturers Representatives, Inc. v.
Dabbs & Stewart, 173 Ga. App. 304, 325 S.E.2d 914 (1985). In that
case, the general contractor sued a supplier who refused to honor its bid.
The general contractor then obtained the materials from another source
and sued the subcontractor for the difference between the price of the
substituted materials and the supplier's bid for the same materials. The
court found no obvious error on the face of the bid and noted that the
supplier had even reaffirmed the bid on several occasions. The general
contractor had relied on the bid in submitting its own bid to the owner.
Forced to choose between two innocent parties, the court found that the
negligent supplier who caused the bid error should bear the loss.
A bid bond is normally given by a bidder on a public or private project
in order to guarantee that the bidder will enter into the contract and
post the required performance and payment bonds in the event that the bidder
is awarded the contract.
If the principal on a bid bond defaults, the liability of the principal
and the surety will ordinarily be limited to the difference between the
amount of the principal's bid and the amount of the next lowest responsible,
responsive bidder.
Both public and private owners who engage in competitive bidding may
wish to protect the integrity of the bidding process by insisting on the
posting of a bid bond. A bid bond usually is taken as a percentage of the
total contract price, but sometimes is required in a stated amount by the
owner.
A bid bond is normally given by a bidder on a public or private project
in order to guarantee that the bidder will enter into the contract and
post the required performance and payment bonds in the event that the bidder
is awarded the contract.
If the principal on a bid bond defaults, the liability of the principal
and the surety will ordinarily be limited to the difference between the
amount of the principal's bid and the amount of the next lowest responsible,
responsive bidder.
Both public and private owners who engage in competitive bidding may
wish to protect the integrity of the bidding process by insisting on the
posting of a bid bond. A bid bond usually is taken as a percentage of the
total contract price, but sometimes is required in a stated amount by the
owner.
A bid bond protects the owner in the event that the general contractor defaults on its obligation to sign a contract with the owner in the amount of the bid. The remedy provided by the bid bond is not the performance of the contract but is instead the payment of a sum of money to compensate the owner for the failure to secure a binding contract.
8. Bid Protests
Bid protests arise when an unsuccessful bidder, usually the "second low" bidder, objects to the award of the contract low bidder. Events which may trigger a bid protest include a low bid which is unbalanced, fails to comply with bidding procedures, or has other defects.
Bid protests usually occur in the context of public work, normally because
the public authority is obligated by law to award the bid to the lowest
responsible, responsive bidder. Hilton Construction Co., Inc. v. Rockdale
County Board of Education, 245 Ga. 533, 266 S.E.2d 157 (1980).
In contrast, private owners who bid work usually include a provision
in the bid solicitation indicating that the owner has complete discretion
to accept or reject any bid, even one which is not low. For this reason,
bid protest in the private sector are rare.
Public authorities may have complicated bid protest procedures or regulations, and if they do, then the contractor seeking to file a bid protest should carefully follow these procedures.
The process for filing a bid protest also may be set out in the bid
package, and this should be carefully examined in order to verify the exact
procedures required to protest the bid.
In Georgia, many public owners have not adopted formal bid protest procedures.
In that is the case, it usually is helpful to call the owner's representative
to inquire about bid protest procedure preferred by the owner. Often the
owner will require nothing more than a letter setting out the grounds for
the bid protest.
Most courts will require that all "administrative" procedures be exhausted
before any judicial action can be taken.
A frustrated bidder normally will be required to seek an injunction
barring the award of a contract to another party or the re-bidding of the
project. Suing to recover lost profits after the contract already has been
awarded to another normally will not be successful.
OTHER RESOURCES
Annot., Standing of Disappointed Bidder on Public Contract to Seek
Damages Under 42 U.S.C. § 1983 for Public Authority's Alleged Violation
of Bidding Procedures, 86 A.L.R. Fed. 907 (1988).
Annot., Recovery from the United States of Cost Incurred by Unsuccessful
Bidder in Preparing and Submitting Contract Bid in Response to Government
Solicitation, 30 A.L.R. Fed. 355 (1976).
CLAIMS FOR CHANGES
9. Changed Conditions Claims
.1 In General
Changes are a fact of life in construction contracting, and successfully
dealing with changes often spells the difference between success and failure
of a contractor. Owners should recognize that changes are inevitable even
on a well-planned project, and should allow for such contingencies in their
schedule and budget.
Construction contracts usually have clauses dealing with any changes
which may arise on the project. Contractors and owners should pay particular
attention to these provisions and should carefully follow the procedural
requirements of the changes clause in order to avoid prejudicing their
rights to recover for changes.
Claims for differing site conditions are very common due to the inherent
difficulty of determining the conditions existing underground or within
the structure of a completed building. Differing site conditions often
significantly increase the cost of construction, create unforeseen delays,
complicate construction techniques, and disrupt the smooth operation of
the project.
.2 Duty to Proceed Despite Unforeseen Difficulties
A contractor performing work under a fixed price contract is not entitled
to additional compensation merely because unforeseen difficulties are encountered
in the performance of the contract. Decatur County v. Praytor, Houston
& Wood, 165 Ga. 742, 142 S.E.2d 678 (1928); Anderson v. Golden,
569 F.Supp. 122 (S.D. Ga. 1982).
.3 Duty to Inspect
Where the contract places a duty on the contractor to inspect and verify
site conditions, this duty will ordinarily be enforced. Jahncke Services,
Inc. v. Department of Transportation, 172 Ga. App. 215, 322 S.E.2d
505 (1984)(contract places duty on contractor to make its own investigation
of borrow pits).
.4 Disclaimer Clauses
Construction contracts often contain a "differing site conditions" clause
to address the issue how responsibility for differing site conditions will
be allocated between the owner and the contractor.
If the owner elects to provide the contractor with site data which was
obtained by the owner's own site investigation, the owner may accompany
that site data with a disclaimer indicating that the owner and site engineer
do not warrant the accuracy or correctness of the data, and that the data
was gathered solely for the owner's use and is provided to the contractor
with that express understanding.
The construction contract also may require the contractor to conduct
its own site inspection, and may completely disclaim any owner responsibility
for unforeseen site conditions. Time may be insufficient for the contractor
to conduct a proper site investigation before a bid must be submitted,
or cost constraints may make an independent site investigation financially
impossible.
Issues frequently arising in the context of differing site conditions
include whether the contractor was on notice of the site conditions due
to site examination, the adequacy of that site examination, whether the
site conditions were reasonably foreseeable by the contractor, whether
the contractor relied upon site data submitted to the contractor by the
owner, whether the site conditions were materially different from those
contemplated in the contract documents or site report, whether the contractor's
means and methods were reasonable and prudent, causation, whether adequate
notice was given, and many others, not all of which have been addressed
by the cases in Georgia.
Merger or disclaimer clauses in the contract also present special problems.
Merger or disclaimer clauses normally provide that the written contract
represents the entire agreement between the parties and supercedes all
prior negotiations, representations, and agreements. Accordingly, if the
contractor sues the owner for fraud without rescending the contract containing
such a merger clause, then the contractor is deemed to have "affirmed the
contract" and accepted its benefits, and thus is estopped from asserting
that representations outside the four corners of the contract caused or
contributed to the contractor's loss.
The Georgia Court of Appeals has observed that the very fact that a
contract contains a provision for extra work necessitated by unforeseen
conditions is evidence enough that not every condition is expected to be
anticipated. State Highway Department v. Wright Contracting Co.,
107 Ga. App. 758, 131 S.E.2d 808 (1963).
Where the contract in question does not contain an unforeseen conditions
clause, unequivocally limits the contract to a sum certain, and contains
an inspection clause, the contract imposes the risk of uncertainty of subsurface
conditions on the contractor. American Demolition, Inc. v. Hapeville
Hotel Limited Partnership, (Ga. App., Case No. A91A1385, Nov. 14, 1991).
.5 Conditions Differing from
Contract Indications
Differing site conditions claims may arise either as a breach of contract
claim or as a tort claim, depending upon how the claim arose. If a construction
contract represents that certain conditions exist on the site, and in fact
the actual conditions on the site differ from those represented in the
contract, then a contract-based claim arises.
A detailed analysis of the modern view on this issue was undertaken
by the court in Robert E, McKee v. City of Atlanta, 414 F.Supp.
957, 959 (N.D. Ga. 1976). In that case, the court noted that if the contract
clearly places the risk of uncertainty on one of the parties, then that
party must absorb the losses resulting from the unexpected condition. But
where the government makes positive statements of material fact concerning
the work in question an implied warranty arises which is not lost by general
exculpatory clauses disclaiming any responsibility for the accuracy of
the data.
The court went on to note that this implied warranty is conditioned
upon a determination of whether the contractor could have discovered the
true facts through a reasonable investigation, given the time available,
as well as the facilities and expense required in order to conduct a suitable
investigation.
Other factors considered are the detailed nature of the government's
data. No relief will be granted, however, for the contractor's own misjudgment
based upon information which is itself accurate. This decision is in accordance
with the majority view on this issue, but the Georgia state courts seem
to have been less willing to embrace this view. For example, the Georgia
courts have held that conditions shown on the plans and specifications
which are expressly made subject to adjustment by the project engineer
do not constitute a misrepresentation of site conditions. Decatur County
v. Praytor, Houston & Wood, 165 Ga. 742, 142 S.E.2d 678 (1928).
.6 Conditions Differing from Those Normally Encountered
As reflected in the foregoing decisions, the contractor usually is not
entitled to recover from the owner for extra expense occasioned by conditions
which differ from those normally encountered. This is particularly true
where the contract places the risk of such conditions on the contractor,
and the owner does not mislead the contractor or misrepresent the actual
job conditions.
.7 Notice
Where the contract requires the contractor to give notice of extra expense
caused by unforeseen site conditions, these provisions ordinarily are enforced.
State
Highway Department v. Hewitt Contracting Company, 113 Ga. App. 685,
149 S.E.2d 499 (1966).
.8 Withholding Information
If the site conditions actually are concealed from the contractor, in
other words, active rather than passive concealment of the conditions,
then the concealment of the site conditions may give rise to a tort claim
for fraud and misrepresentation. Robert E. McKee, Inc. v. City of Atlanta,
414 F.Supp. 957 (N.D. Ga. 1976).
Where county officials or the project engineer are responsible for the
fraud, they may be personally liable. Decatur County v. Praytor, Houston
& Wood, 165 Ga. 742, 142 S.E.2d 678 (1928).
The contractor must make an election either to affirm the contract and
sue for breach of contract, or to rescind the contract and sue for fraud.
Suing for fraud requires a careful consideration of the legal elements of the fraud claim and a cautious approach to the analysis of the provisions of the contract and its effect on the fraud claim.
10. Defensive Use of Change Orders
The issuance and acceptance of a change order usually is considered conclusive resolution of all of the costs or time extensions covered by the change order. In some cases, the Georgia courts have reached this conclusion by finding that the acceptance of a change order by the subcontractor constitutes an "accord and satisfaction" of all matters dealt with in the change order.
A change order is not always conclusive. Change orders unilaterally
issued by the general contractor may be considered an "offer" which can
be accepted or rejected by the subcontractor.
Furthermore, a subcontractor may be able to avoid the conclusive effect of a change order by proving the existence of a separate and distinct collateral agreement. For example, in J.L. Williams & Company, Inc. v. West Concrete Company, 139 Ga. App. 208, 228 S.E.2d 196 (1976), the court held that neither the execution of a "wrap up" change order dealing with certain claims and backcharges relating to the subcontractor, nor the execution of a lien waiver and affidavit by the subcontractor waiving rights against the owner (to which the general contractor was not a party), precluded the existence of a separate and distinct oral agreement of the general contractor to pay for certain payroll expenses of the subcontractor. Although these documents were evidence casting doubt upon the existence of a separate and collateral oral agreement, under the circumstances of the case the court found that a question of fact was presented as to whether the change order constituted an accord and satisfaction intended to extinguish the oral agreement along with the subcontractor's other claims.
11. Constructive or Verbal Change Orders
.1 Generally
When one renders a service which is valuable to another and that service
is accepted by the other party, there arises an implied promise to pay
for the reasonable value of that service. O.C.G.A. § 9-2-7.
"Even if there is an express contract, if services not contemplated
by the original agreement become necessary to achieve the contractually
objective and are rendered and accepted, the law implies and enforces performance
of a promise to pay for such extra services." Puritan Mills, Inc. v.
Pickering Construction Co., 152 Ga. App. 309, 262 S.E.2d 586 (1979);
Fruin-Colnon
Corp. v. Air Door, Inc., 157 Ga. App. 804, 278 S.E.2d 708 (1981)(cost
of extra engineering services).
An implied promise to pay for extra work arises by a showing that the
owner required the contractor to perform extra work in addition to the
work for which a contract priced had been fixed. Gardner v. Tarpley,
120 Ga. App. 192, 169 S.E.2d 690 (1969); Finn v. Carden, 100 Ga.
App. 270, 110 S.E.2d 693 (1959)(contractor directed by owner to perform
any extra work ordered by owner's wife); Johnson v. Freeman, 160
Ga. App. 431, 287 S.E.2d 314 (1981).
Where both the owner and the general contractor authorize and
accept extra work performed by a subcontractor, then an implied promise
to pay for the reasonable value of the extra work arises by operation of
law, and both the owner and the general contractor may be sued by the subcontractor.
Conway
v. Housing Authority of the City of Atlanta, 102 Ga. App. 333, 116
S.E.2d 331 (1960).
Likewise, where it is proven that the owner alone expressly authorized
and requested the subcontractor to perform extra work directly for the
owner, and the owner accepts the services and benefits provided by the
subcontractor, then owner may be held liable for the reasonable value of
the services provided by the subcontractor. Highsmith v. National Linen
Service Corp., 63 Ga. App. 112, 10 S.E.2d 237 (1940).
The element of knowledge and consent to the performance of the
extra work, either express or implied, is a critical element of the implied
promise to pay. Where the work is performed without the knowledge, authority,
consent or ratification of the owner, then an implied promise to pay for
the work does not arise. Lawson v. O'Kelley, 81 Ga. App. 883, 60
S.E.2d 380 (1950); Mayor of Brunswick v. Sims, 14 Ga. App. 315,
80 S.E. 730 (1914).
.2 Contracts Requiring Written Change Orders
Most construction contracts prohibit changes without the prior written
approval of the owner. Some contracts go further, and bar payment for any
work performed without a written change order.
As a general rule, in the absence of facts proving waiver or estoppel
by a showing of some affirmative authorization to perform the extra work,
the provisions of a building contract requiring notice, prior approval,
and the issuance of a written change order before the performance of extra
work are valid and enforceable. State Highway Department v. Hewitt Contracting
Company, 113 Ga. App. 685, 149 S.E.2d 499 (1966)(failure to give contractually-required
notice bars contract claim).
For example, in Heard v. Dooly County, 101 Ga. 619, 28 S.E. 986
(1897), the court enforced a contract provision barring any payment for
extra work performed without a prior estimate and written authorization.
See
Town of Decatur v. Jaudon, 136 Ga. 854, 72 S.E. 351 (1928);
Grahn
Construction Co. v. Pridgen, 49 Ga. App. 720, 176 S.E. 656. In these
cases there was no allegation or proof of an express agreement by the defendant
to pay for the alleged extra work, and that the changes were not necessary
to the completion of the original job.
In Cobb v. Bond, 39 Ga. App. 637, 148 S.E. 411, the contractor
entered into a contract providing that the owner was entitled to make changes
in the work and there was no provision for additional payment for these
changes. The court held under these circumstances the contractor was not
permitted to recover additional payment for the changes.
The courts in Georgia have held, however, that such a provision does
not always bar a recovery by the contractor for work performed without
a written change order. Provisions such as these are not intended to bar
the contractor from recovering for extra work added by the owner which
was not within the scope of work of the original contract. Finn v. Carden,
100 Ga. App. 270, 110 S.E.2d 693 (1959)(contract claim barred because approval
received from architect, but
quantum meruit recovery permitted
on implied obligation to pay for extra work ordered by owner's wife).
Georgia law provides that when the parties to a contract mutually depart
from its terms and pay or receive money under such departure, the contract
term is suspended until reasonable notice is given to the other party stating
the intention to return to the exact terms of the written agreement. O.C.G.A.
§ 13-4-4.
Accordingly, where the parties by a course of conduct mutually depart
from the strict terms of the contract and operate without prior written
change orders there may be a waiver of this contract provision or an oral
variation of the provisions of the contract. Biltmore Construction Co.
v. Tri-State Electric Contractors, Inc., 137 Ga. App. 504, 224 S.E.2d
487 (1976);
Clark v. Belleau, Inc., 114 Ga. App. 587, 151 S.E.2d
894 (1966)(engineer's approval waived); State Highway Department v.
Wright Contracting Co., 107 Ga. App. 758, 131 S.E.2d 808 (1963)(engineer's
failure to act after notice of claim waives contract requirement of prior
written agreement).
A mutual departure from the contract occurs when the owner, without
claiming that the work is covered by the contract, orally orders extra
work with notice that the contractor regards the work as extra and expects
additional compensation for it, the contractor can recover for the value
of the work despite the fact that there is a stipulation in the contract
requiring that all changes be ordered in writing. State Highway Department
v. Wright Contracting Co., 107 Ga. App. 758, 131 S.E.2d 808 (1963);
State
Highway Department v. Hewitt Contracting Company, 113 Ga. App. 685,
149 S.E.2d 499 (1966).
The same rule applies to prime contractors who orally order extra work
from subcontractors. Mion Chemical Corp. v. Daniel Construction Co.,
111 Ga. App. 369, 141 S.E.2d 839 (1965)(subcontractor's extra work occasioned
by faulty work of prime contractor); Clark v. Belleau, Inc., 114
Ga. App. 587, 151 S.E.2d 894 (1966)(court allows subcontractor quantummeruit
recovery where contractor-owner's superintendent agrees to pay for removal
of muck as an extra); Pro Metal Building Systems, Inc. v. T.E. Driskell
Grading Co., Inc., 170 Ga. App. 127, 316 S.E.2d 574 (1984)(recovery
permitted for rework caused by general contractor); Excavators and Erectors,
Inc. v. Bullard Engineers, Inc. 489 F.2d 318 (5th Cir. 1973)(separate
oral agreement to pay subcontractor for cost of replacing unsuitable soil).
The courts reason that the owner should not be permitted to mislead
the contractor into thinking that the work will be paid for, and then enjoy
the fruits of the contractor's labor without paying for the contractor's
services. In other words, under these circumstances, the courts will not
permit a forfeiture of the rights of the contractor merely because the
the failure to comply with the formal prerequisites of the contract. McDaniel
v. Mallary Brothers Machinery Co., 6 Ga. App. 848, 66 S.E. 146.
The extra work also may be ordered by the owner's architect. Where the
architect is given authority to order extra work and acts within this authority
to direct the contractor to perform extra work, then the owner is obligated
to pay for the extra work ordered by the architect. Continental Casualty
Company v. Wilson-Avery, Inc., 115 Ga. App. 793, 156 S.E.2d 152 (1967).
In much the same way, where a subcontractor places the general contractor
on notice of a claim for extra work which is denied by the general contractor,
and both parties are equally well-informed about what is required to do
the work, then the subcontractor may be excused from strictly following
the change order requirments of the contract. Batson-Cook Company v.
Loden & Company, Inc., 129 Ga. App. 376, 199 S.E.2d 591 (1973).
In order to be valid, the subsequent oral modification must be supported
by separate consideration. Willingham Sash etc. Co. v. Drew, 117
Ga. 850, 45 S.E. 237; Brookhaven Landscape & Grading Co., Inc. v.
J.F. Barton Contracting Co., 676 F.2d 516 (11th Cir. 1982)(finding
no consideration for that portion of the contractor's claim which included
work covered by the original scope of work for the project).
Sufficient consideration to support an oral modification of a written
contract is provided where the builder makes alterations which entail the
outlay of additional expenses and costs pursuant to the owner's direction,
and the owner subsequently accepts the building as altered and occupies
it. Bailey v. Martin, 101 Ga. App. 63, 112 S.E.2d 807 (1960).
OTHER RESOURCES
Annot., Effect of Stipulation in Public Building or Construction
Contract That Alterations or Extras Must Be Ordered in Writing, 1 A.L.R.3d
1273 (1965).
Annot., Effect of Stipulation, in Private Building or Construction
Contract, That Alterations or Extras Must Be Ordered in Writing, 2
A.L.R.3d 620 (1965).
CONTRACT PERFORMANCE AND PAYMENT CLAIMS
12. Breach of Contract
.1 In General
There are countless Georgia cases dealing with breach of contract in
the context of a construction contract. It almost goes without saying that
where a contractor enters into a contract to perform in accordance with
plans and specifications furnished by the owner, and the contractor breaches
that contract, the contractor is liable for the breach to the owner.
Restitution, damages and specific performance are the three remedies
for breach of contract. PMS Construction Co., Inc. v. DeKalb County,
243 Ga. 870, 257 S.E.2d 285 (1979)(citing 5 Corbin on Contracts §§
1102-1121). Other methods of collecting damages for breach of a construction
contract include quantum meruit and constructive trust.
.2 Restitution
The object of the remedy of restitution is to return the injured party
to the position he occupied before his performance. In other words, to
restore him to the pre-contract status quo. Restitution is an alternative
remedy to a breach of contract suit which entitles a party whose express
contract has been breached or repudiated to recover the reasonable value
of materials furnished and services rendered, measured as of the time of
performance. PMS Construction Co., Inc. v. DeKalb County, 243 Ga.
870, 257 S.E.2d 285 (1979); Decatur County v. Praytor, Howton, &
Wood Contracting Co., 163 Ga. App. 929, 137 S.E. 247 (1928).
.3 Damages
Damages recoverable for a breach of contract are such as arise naturally
and according to the usual course of things from such breach. They must
be within the contemplation of the parties when the contract was made as
the probable consequence of its breach. O.C.G.A. § 13-6-2.
The courts in Georgia have not been completely clear about how this
standard is to be applied. What is clear is that the standard will be different,
depending upon the circumstances of the breach.
The proper measure of damages for the breach of an express contract
by the building contractor is the difference in the fair market value of
the project as it was constructed by the contractor and the fair market
value of the project as it ought to have been constructed in accordance
with the contract between the parties. Kendrick v. White, 75 Ga.
App. 307, 43 S.E.2d 285 (1947); McKee v. Wheelus, 85 Ga. App. 525,
69 S.E.2d 788 (1952); Classic Restorations, Inc. v. Bean, 155 Ga.
App. 694, 272 S.E.2d 557 (1980); Hortman v. Cantrell, 173 Ga. App.
429, 326 S.E.2d 779 (1985); Jim Walter Homes, Inc. v. Strickland,
185 Ga. App. 306, 363 S.E.2d 834 (1987).
A second acceptable measure of damages for defective workmanship is
the cost of repair of the defects. Small v. Lee & Bros., 4 Ga.
App. 395, 61 S.E. 831 (1908); Dougherty v. Simpson, 190 Ga. App.
718, 380 S.E.2d 57 (1989). This measure will not be applied where it will
result in economic waste. Ideal Pool Corp. v. Hipp, 187 Ga. App.
273, 370 S.E.2d 32 (1988).
The proper measure of damages recoverable by a contractor when the owner
wrongfully breaches a construction contract was set out in the case of
Williams
v. Kerns, 153 Ga. App. 259, 265 S.E.2d 605 (1980). In essence, this
figure is the net profit to which the builder would have been entitled
had full performance of the contract been permitted.
That net profit figure is reached by subtracting from the contract price
the amount which full performance would have cost the contractor.
If performance by either party had begun prior to the breach, adjustments
must be made to ensure that the contractor receives the full amount of
the profit, but no more. The court set out a formula to reach this figure.
First, there must be added to the profit figure the amount of the contractor's
net loss up to the point of the breach. That figure is reached by subtracting
from the expenses incurred by reason of the contractor's performance the
salvage or resale value of the material left on hand. The sum of those
figures (the profit which would have been realized from full performance
plus net loss incurred by performance to the date of breach) may in no
event exceed the contract price.
Second, there must be deducted from the recovery those amounts received
by the contractor from the owner as prepayment or progress payment.
.4 Specific Performance
Specific performance of a contract may be ordered by a court where performance
of a contract is within the power of a party and where damages for breach
of the contract would not be adequate compensation for the breach. O.C.G.A.
§ 23-2-130.
.5 Constructive Trust
A number of states have adopted statutes that require a general contractor
who is paid by the owner in amounts which in part represent payments owed
to its subcontractors and suppliers to hold this money in trust for the
benefit of those parties. Georgia has no such statute.
Although Georgia is not a "trust fund" state it does, however, have
court decisions which recognize the constructive trust fund theory on equitable
grounds. Bethlehem Steel Corporation v. Tidwell, 66 B.R. 932 (M.D.
Ga. 1986)(citing Georgia authority for "construction" or "constructive"
trusts).
.6 Quantum Meruit
In the absence of a contract affording a party a legal right to recover
for goods and services provided to another, the party may assert a claim
in equity for a "quantum meruit" recovery for the reasonable value of the
goods and services which were provided to the other party. Such a recovery
is based upon a legally implied promise to pay for the reasonable value
of goods and services which are accepted by another. In Georgia, this right
to recover in quantum meruit is stated in O.C.G.A. § 9-2-7, which
states:
Ordinarily, when one renders service or transfers property which is
valuable to another, which the latter accepts, a promise is implied to
pay the reasonable value thereof....
This remedy is not available, however, where the parties have entered
into an express contract for the delivery of such goods and services. "There
can be no recovery in quantum meruit when the action is based on an express
contract." Stowers v. Hall, 159 Ga. App. 501, 283 S.E.2d 714 (1981).
The measure of damages recoverable under quantum meruit is limited to
the value received by the party receiving the goods and services. Pembrook
Steel Co. v. Technical Sales Assoc., 138 Ga. App. 744, 227 S.E.2d 491.
Evidence of this value is often provided by the testimony of an expert
witness who testifies as to the value provided by the plaintiff. As an
evidentiary matter, the cost of labor and materials used in performing
the work is relevant to show the value of the improvements made, although
it is the responsiblity of the judge or jury to determine the actual value
of the improvements made. Maloy v. Ewing, 157 Ga. App. 95, 276 S.E.2d
145.
This remedy of quantum meruit or implied contract is not available when a county is a defendant, as a result of O.C.G.A. § 36-10-1, which requires that all contracts entered into by a county governing authority be in writing and entered on its minutes. PMS Construction Co., Inc. v. DeKalb County, 243 Ga. 870, 257 S.E.2d 285 (1979).
13. Inspection and Quality Control
.1 Overinspection Claims
Where the architect requires stricter inspection or quality standards
than those set out in the specifications, and the contractor properly protests
compliance with these higher standards, then the contractor may recover
for these extra costs. Batson-Cook Company v. Loden & Company, Inc.,
129 Ga. App. 376, 199 S.E.2d 591 (1973).
.2 Industry Standards
A wide variety of sources exist for establishing industry standards
for performance of a construction contract. The typical way in which such
standards are proven is by way of expert testimony. Such testimony is admissible
to show the custom and practice of a construction trade. Biltmore Construction
Co., Inc. v. Tri-State Electrical Contractors, Inc., 137 Ga. App. 504,
224 S.E.2d 487 (1976);
Puritan Mills, Inc. v. Pickering Construction
Co., Inc., 152 Ga. App. 309, 262 S.E.2d 586 (1979).
.3 Architect or Engineer's Approval
Ordinarily, where the contract makes the decision of the architect or
engineer binding on the contractor, such a provision will be enforced.
Finn
v. Carden, 100 Ga. App. 270, 110 S.E.2d 693 (1959).
Where the contract makes engineer's decision in certain matters final,
in the absence of fraud or such gross mistake as would necessarily imply
bad faith or a failure to exercise an honest judgment, then the contractor
may not recover for costs associated with the engineers decision, even
if the contractor proves that decision is erroneous. State Highway Department
v. Hewitt Contracting Company, 113 Ga. App. 685, 149 S.E.2d 499 (1966).
This rule does not extend to errors in calculation or other such mistakes
not related to engineering judgment. State Highway Department v. Hewitt
Contracting Company, 113 Ga. App. 685, 149 S.E.2d 499 (1966).
14. Specification Disputes
In the typical construction contract the owner provides the general
contractor with a set of plans and specifications prepared by the owner's
architect or engineer. The contractor is asked to build the project in
accordance with those plans and specifications and not to deviate from
those plans and specifications without the permission of the owner.
Under these circumstances, if the completed project is unsatisfactory
to the owner for some reason but the contractor followed the plans and
specifications in building the project, the courts have been reluctant
to hold the contractor responsible for any deficiencies in the completed
structure.
Where a contractor signs a contract agreeing to construct a project
in accordance with plans and specifications prepared by the owner, the
contractor is not responsible for the consequences of defects in the plans
and specifications. United States v. Spearin, 248 U.S. 132, 136
(1918). Spearin has been cited with approval in Georgia. Decatur County
v. Praytor, Houston & Wood, 165 Ga. 742, 142 S.E.2d 678 (1928).
The contractor is not responsible for unsatisfactory results attributable
solely to defects in the owner's plans and specifications. Batson-Cook
Co. v. R.C. Pierce Roofing Co., 124 Ga. App. 835, 186 S.E.2d 358 (1971).
In Decatur County v. Praytor, Houston & Wood, 165 Ga. 742,
142 S.E.2d 678 (1928), the Georgia Supreme Court held that where a unit-price
contract gives the project engineer discretion to change the stated elevation
of certain piers shown on the owner's plans and specifications, then there
is no implied warranty that the piers will be built at the elevations shown
on the plans and specifications.
In State Highway Dept. v. Hewitt Contracting Co., 113 Ga. App.
685, 149 S.E.2d 499 (1966), the court again held that there was no implied
warranty of the plans and specifications by the owner, where the terms
of a State Highway Department contract which warned that there may be errors
in the plans and specifications and provided for the contractor to be compensated
for the actual work done upon completion of the contract, including compensation
for any additional work required because of errors or changes in the plans
and specifications.
Where the contractor is consulted by the owner in establishing the specifications,
and the contractor knows that the owner is relying upon the contractor's
expertise, the contractor may not set up as a defense the improper specifications
of the owner. Talerica v. Grove Park Plumbing Service, 103 Ga. App.
591, 120 S.E.2d 36 (1961).
OTHER RESOURCES
Annot., Construction Contractor's Liability to Contractee for Defects
or Insufficiency of Work Attributable to the Latter's Plans and Specifications,
6 A.L.R.3d 1394 (1966).
15. Termination Claims
.1 Wrongful Termination
Where a contractor is wrongfully terminated, an action will lie for
the damages caused by the wrongful termination. Stowers v. Hall,
159 Ga. App. 501, 283 S.E.2d 714 (1981); Marathon Oil Company v. Hollis,
167 Ga. App. 48, 305 S.E.2d 864 (1983).
In order to avoid problems in cases of voluntary termination, the better
practice is to obtain from the defaulting party an acknowledgement of default
or some form of admission that there has been a material breach of contract.
The acknowledgement of default also should include a final lien waiver
in the proper statutory form acknowledging that any payments which have
been previously received constitute full and final payment under the contract.
Although O.C.G.A. § 44-14-361.1(a)(1) requires "substantial compliance"
with the construction contract as a condition precedent for a lien filing,
this seldom deters a lien filing.
.2 Termination for Convenience
The modern trend is to permit the owner to terminate its contract with
the general contractor for "convenience," meaning that there is no requirement
for the owner to show cause for the termination. In such clauses, the owner
usually agrees to pay for the contractor's direct costs of demobilization,
but not for any lost profits on the job.
Such clauses do not always insulate the owner from liability to the general contractor. See Department of Transportation v. Arapaho Construction, Inc., 180 Ga. App. 341, 349 S.E.2d 196 (1986).
16. Contractor's Right to Stop Work
or Rescind Contract
A contractor entering into a contract containing a disputes clause must
follow the disputes procedure set out in that clause and may not simply
stop work because of payment disputes with the general contractor. Keyway
Contractors, Inc. v. Leek Corporation, Inc., 189 Ga. App. 467, 376
S.E.2d 212 (1988).
A contractor who partially performs a contract and then voluntarily
abandons further performance without fault of the other party or the other
party's consent, cannot sue to recover damages for the part performance.
Ramco
Roofing & Supply Co., Inc. v. Kaminsky, 156 Ga. App. 708, 275 S.E.2d
764 (1980).
A subcontractor may not withhold a warranty which is made an express
condition precedent to payment under a contract on the grounds that the
general contractor's failure or anticipated breach of its obligation to
pay the subcontractor. Dixie Roof Decks, Inc. v. Borggren/Dickson Construction,
Inc., 195 Ga. App. 881, 395 S.E.2d 19 (1990).
The Georgia courts have recognized actions to recover for anticipatory
breach of contract. See Peachtree Medical Building, Inc. v. Keel,
107 Ga. App. 438, 130 S.E.2d 530 (1963).
A party may rescind a contract without the consent of the opposite party
on the ground of nonperformance by that party, but only when both parties
can be restored to the condition in which they were before the contract
was made. O.C.G.A. § 13-4-62.
A contract may be rescinded at the instance of the party defrauded,
but in order to rescind the contract, the defrauded party must promptly
upon discovery of the fraud restore or offer to restore to the other party
whatever he has received by virtue of the contract, if it has any value.
O.C.G.A. § 13-4-60.
A contractor who continues to perform despite having grounds for rescending the contract will be deemed to have waived its right to rescind the contract. State Highway Department v. Hewitt Contracting Co., 221 Ga. 621, 146 S.E.2d 632 (1966).
17. Scope of Work Disputes
.1 Extra Work Claims
Scope of work disputes are an extremely common souce of construction
claims. Most contracts define the contractor's scope of work broadly, to
include all work reasonably necessary to accomplish the the work set out
in the contract, or referenced in the plans and specifications.
What happens when there is a conflict between the scope of work as set
out in the contract, and the scope of work described in the plans and specifications?
In Eller & Heyward, Inc. v. Jackson, 117 Ga. App. 753, 162 S.E.2d
238 (1968), a subcontractor contended that the subcontract requiring installation
of gutters and downspouts conflicted with the construction drawings for
the project which showed that no gutters and downspouts were to be installed.
The court declined to determine as a matter of law whether one or the other
of the documents controlled, and found that on the facts of this case the
meaning of the contract was an issue of fact which was properly submitted
to the jury for a determination of the intention of the parties.
.2 Claims for Quantity Variation Quantities
Where a contract provides unit prices for quantities called out in a contract, the Georgia courts have not been particularly receptive to claims for extra expense caused by the variation from the estimated quantities. See State Highway Department v. MacDougald Construction Co., 102 Ga. App. 254, 115 S.E.2d 863 (1960); Western Contracting Corporation v. State Highway Department, 125 Ga. App. 376, 187 S.E.2d 698 (1972); Department of Transportation v. Claussen Paving Company, 246 Ga. 807, 273 S.E.2d 161 (1980)(owner admitted estimated quantities were wrong).
18. Duty to Coordinate and Cooperate
Every contract imposes a duty of good faith and fair dealing in its performance and its enforcement. Restatement (Second) of Contracts § 231; O.C.G.A. § 11-1-203.
This means that there should be substantial compliance with both the
letter and the spirit of the contract. Crooks v. Chapman Co., 124
Ga. App. 718, 185 S.E.2d 787 (1971).
Where a party breaches the duty of good faith and fair dealing, the
party may be precluded from insisting on strict compliance with the terms
of the contract.
West v. Koufman, 259 Ga. 505, 384 S.E.2d 664 (1989)(party
solicited filing of false liens).
If the nonperformance of a party to a contract is caused by the conduct
of the opposite party, then this conduct excuses the other party from performance.
O.C.G.A. § 13-4-23.
Georgia also has a bad faith statute which authorizes the recovery of
attorneys' fees and expenses of litigation where a defendant acts in bad
faith. O.C.G.A. § 13-6-11.
Where a subcontract requires a subcontractor to coordinate its shop drawings with the work of other trades, the subcontractor is responsible for the failure to coordinate its drawings with conflicting trades, notwithstanding the fact that the general contractor has assumed this same obligation with respect to the owner. High Point Sprinkler Company of Atlanta v. George Hyman Construction Co., 164 Ga. App. 706, 297 S.E.2d 757 (1982).
19. Warranty Claims
Most construction contracts contain warranty provisions which state
that the contractor or subcontractor warrants its work for some period
of time, normally one year.
The general conditions in most standard form contracts state that the
warranty period are not an exclusive remedy. In other words they do not
limit a breach of contract claim to the one-year period set out in the
warranty. The statute of limitations for such claims which arise under
a written contract is six years. O.C.G.A. § 9-3-24. SeeMcDevitt
& Street Co. v. K-C Conditioning Service, Inc., Ga. Ct. App. A91A1955
(March 18, 1992).
There is an implied warranty in every contract for work or services
a duty to perform it skillful, careful, diligent, and workmanlike manner.
Howell
v. Ayers, 129 Ga. App. 899, 202 S.E.2d 189 (1973).
Contract provisions in building or construction contracts which attempt
to insulate the contractor from its sole negligence are prohibited by statute
in Georgia. O.C.G.A. § 13-8-2(b). This statute has been construed
as prohibiting warranty language which has this same effect. Bicknell
v. Richard M. Hearn Roofing & Remodeling, Inc., 171 Ga. App. 128,
318 S.E.2d 729 (1984).
Georgia recognizes the rule that neither caveat emptor nor merger by
deed is a viable defense by a builder-seller against a homeowner's tort-negligence
and breach of contract claims seeking recovery for latent building construction
defects about which the purchaser homeowner did not know and in the exercise
of ordinary care would not have discovered, which defects were either known
to the builder-seller or in the exercise of ordinary care would have been
discovered by him. Worthey v. Holmes, 249 Ga. 104, 287 S.E.2d 9
(1982).
There are a variety of warranties under the Uniform Commercial Code
which apply to the sale of goods. These warranties include both express
and implied warranties, including warranties of merchantability and fitness
for an intended purpose.
20. Payment
.1 Joint Check Agreements
Suppliers frequently encounter situations in which joint checks (sometimes
called "two-party" checks) are issued payable to both the supplier and
a subcontractor. Joint checks also may be used where a contractor is faced
with a thinly capitalized subcontractor, and the sub's bank insists on
the issuance of a check made payable jointly to the sub and the bank. Occasionally,
a surety may require that checks be made payable both to the surety and
its principal, or may itself issue joint checks to third parties making
claim on a payment bond. Although the use of joint checks is common, surprising
results may occur if care is not used to properly handle a joint check.
What is a joint check? A joint check is considered to be any check made
payable to two or more parties (called "payees"). The effect of a joint
check differs depending upon how the check is made out. A check payable
to "John Doe and John Smith" is a check made payable to joint payees
and must be endorsed by both of them before being cashed. A check made
payable to "John Doe and/or John Smith" is made payable to alternative
payees, and may be cashed by either of them without the signature of
the other. Most contractors will be surprised to know that a check made
payable to "John Doe/John Smith" also is made payable to alternative
payees and may be cashed by either one of them. Ryland Group, Inc.
v. Gwinnett County Bank, 151 Ga. App. 148, 259 S.E.2d 152 (1979).
Joint checks normally are issued pursuant to a formal joint check agreement.
The joint check agreement may be made by a contract (Williams v. McCoy
Lumber Industries, Inc., 146 Ga. App. 380, 246 S.E.2d 410 (1978));
by letter agreement (Century Engineering and Construction, Inc. v. American
Olean Tile Co., 172 Ga. App. 769, 324 S.E.2d 591 (1984)); or by an
oral agreement (All-Phase Electric Supply Company v. Transamerican Insurance
Company, 162 Ga. App. 104, 290 S.E.2d 208 (1982)).
It is important to remember that a joint check agreement must have consideration
in order to be valid. A mere "naked promise" to include a party on a joint
check does not create a valid obligation to comply with the promise. Trust
Company of Columbus v. Rhodes, 144 Ga. App. 816, 242 S.E.2d 738 (1978).
Forbearance from rescinding a contract or forbearance from suing for a
breach of contract does, however, constitute sufficient consideration
for a joint check agreement. Mann Electric Co. v. Webco Southern Corp.,
194 Ga. App. 541, 390 S.E.2d 905 (1990).
A joint check agreement does not automatically make the party agreeing
to issue the joint check a surety or guarantor of payment for labor and
materials delivered to a job. Century Engineering & Construction,
Inc. v. American Olean Tile Company, 172 Ga. App. 769, 324 S.E.2d 591
(1984); All-Phase Electric Supply Company v. Transamerican Insurance
Company, 162 Ga. App. 104, 290 S.E.2d 208 (1982); Williams v. McCoy
Lumber Industries, Inc., 146 Ga. App. 380, 246 S.E.2d 410 (1978).
What should be considered before a joint check agreement is signed?
First, the prudent contractor or supplier should remember to preserve all
lien rights. A joint check agreement should be carefully reviewed to determine
whether it contains a lien waiver, lien release, or lien subordination
limiting the right to file a lien. Certainly consider filing a lien unless
adequate assurance of payment is received from the co-payee or suitable
arrangements are made for direct payment by the owner before your
lien rights expire.
Second, be sure to check every joint check agreement for time limits,
notice requirements, or any dollar limit on the total amount of joint checks
which will be issued.
Third, from the contractor or supplier's standpoint, it is beneficial
if the joint check agreement contains a guaranty arrangement assuring the
joint payee of payment in the event of a default by the co-payee. Owners
usually will object to such an arrangement on the grounds that they have
no effective control over the co-payee. Despite that objection, a guaranty
agreement may be negotiated where the owner has need of specially fabricated
equipment, material, or labor, or where timely delivery is possible only
from a particular contractor or supplier. Negotiating leverage is much
stronger before delivery than after.
Another frequently encountered problem is the endorsement of joint checks.
There are numerous endorsement problems, including forged endorsements,
missing endorsement of a joint payee, or obliteration of the joint payee's
name from the check.
A forged endorsement occurs when the joint payee's name is fraudulently
signed by the co-payee of a joint check. Falsely endorsing a joint check
in this fashion constitutes the criminal act of forgery. Oldham v. State,
179 Ga. App. 730, 347 S.E.2d 698 (1986).
A more common problem is the attempt to cash a check without the endorsement
of one of the joint payees. A check payable to joint payees must be endorsed
by all of them. O.C.G.A. § 11-3-116(b). A bank which is presented
with a joint check endorsed by only one of the payees normally will refuse
payment of the check. Where, however, a bank cashes a check endorsed by
only one of two joint payees, then the bank, the payor, and the payor's
surety (if any) all are liable to the non-signing payee. Insurance Company
of North America v. Atlas Supply Company, 121 Ga. App. 1, 172 S.E.2d
632 (1970);
Refrigeration Supplies, Inc. v. Bartley, 144 Ga. App.
141, 240 S.E.2d 566 (1977);
Citizens and Southern National Bank v. Sun
Belt Electrical Constructors, Inc. (In reSun Belt Electrical Constructors,
Inc.), 64 B.R. 377 (N.D. Ga. 1986). See Annot., 47 A.L.R.3d
537 (1973). A bank does, however, have the limited right to add an endorsement
of its own depositor where the check is being deposited to that depositor's
account. See O.C.G.A. § 11-4-205.
What happens if the names of joint payees are scratched off by the depositor?
Again, if all of the payees on a joint check have not endorsed the check,
then the bank should refuse to pay the check. It makes no difference that
one of the names on a joint check has been scratched off by the depositor.
Where a bank accepts a check where the name of a joint payee is obliterated
from the check, then the bank accepting the check will be liable for its
failure to dishonor the check. First National Bank of St. Paul v. Trust
Company of Cobb County, 510 F.Supp. 651 (N.D. Ga. 1981).
What if you are the issuer of a check that is improperly cashed without
proper endorsement? The issuer of a joint check has a duty to examine the
joint check when it is returned by the bank in order to verify that it
is properly endorsed. In most states, there is a one-year limitation period
on reporting improper payment due to a missing endorsement. Claims made
against the bank after that one-year period are untimely. Trust Company
Bank v. Atlanta IBM Employees Federal Credit Union, 245 Ga. 262, 264
S.E.2d 202 (1980).
The issuer of a joint check also should issue remittance instructions
indicating how the funds paid by the joint check are to be allocated. Without
such instructions, the payee may apply the funds received to any debt of
the payor. Piedmont Engineering & Construction Corp. v. Hanna Paint
Company, 95 Ga. App. 605, 98 S.E.2d 137 (1955). This could mean that
the payment could be directed to a debt other than the one for which the
check was intended. This leaves open the possibility of double payments
due to mechanic's liens or claims against a payment bond.
Similarly, if the joint payee does not object, the co-payee may allocate
funds (as between the two) in any manner he wishes. Lewis v. Sherwin
Williams Company, 141 Ga. App. 53, 232 S.E.2d 392 (1977). Thus, the
payment could be directed to old invoices, interest, or to debt on unrelated
projects. This could expose the joint payee to liability to the issuer
of the joint check, particularly where the co-payee asserts valid lien
or bond rights against the issuer of the joint check.
As a result of these problems, many jurisdictions follow the "Joint
Check Rule." Under the Joint Check Rule, a supplier endorsing a joint check
without collecting the proceeds of the check is barred from asserting a
lien or bond claim based on that debt. This rule is based on the understanding
that a joint check arrangement is designed to protect the issuer of the
joint check from the supplier's claim, to protect the supplier by ensuring
payment, and to protect the owner from potential lien claims. The reasoning
behind the rule varies from jurisdiction to jurisdiction, but usually is
based upon the legal defenses of payment, release, waiver, or estoppel.
In contrast, a refusal to accept a joint check usually does not bar
the subcontractor from filing a lien or asserting a claim against a payment
bond. This is because the mere issuance of the check does not constitute
payment. Without both endorsements, a joint check is for all practical
purposes a non-negotiable instrument. Piedmont Engineering & Construction
Corp. v. Amps Electric Co., Inc., 162 Ga. App. 564, 292 S.E.2d 411
(1982).
What is the effect of the bankruptcy of one of the joint payees? Difficulties
frequently encountered in this are include possible preference problems
for payments received within ninety days of the filing of the bankruptcy
petition, the problems of handling checks which the bankrupt joint-payee
has not yet signed, and the problems associated with a two-party check
issued in satisfaction of pre-petition shipments. With respect to preference
problems, a debtor filing for bankruptcy is presumed to be insolvent during
the ninety-day period preceding the bankruptcy filing. Joint checks cashed
during this period may be challenged as preferential payments, and a joint
payee may be asked to return money received from joint checks to the debtor's
bankruptcy estate. In jurisdictions with construction trust fund statutes,
or in jurisdictions where courts recognize the construction trust fund
theory on equitable grounds, the joint payee usually will prevail against
the trustee. Bethlehem Steel Corporation v. Tidwell, 66 B.R. 932
(M.D. Ga. 1986).
In states without the protection of an express or implied construction
trust fund doctrine, this result is much less certain. In those states,
the joint payee must establish an exception to the preference or else return
the funds to the bankruptcy estate. Accordingly, in these states a party
receiving a joint check should always be mindful of the fact that funds
received by way of a joint check may be lost as an avoidable preference
at a later date.
A related problem occurs where a joint check has been issued but where
it has not been signed by the debtor. The courts in trust fund jurisdictions
have treated the obligation to sign a joint check as an "executory contract"
which the debtor must either accept or reject. In this situation the debtor
usually will be encouraged or even directed to sign the joint check, particularly
where payment of the check will result in the satisfaction of a claim against
the bankruptcy estate. In re Sun Belt Electrical Constructors, Inc.,
56 B.R. 686 (N.D. Ga. 1986). Jordan Company v. Bethlehem Steel Corporation,
309 F. Supp. 148 (S.D. Ga. 1970).
With respect to the problem of post-petition payments made by a joint
check, the bankruptcy court normally will have to deal with the tension
between the cash collateral security interest of the debtor's bank as opposed
to the claims against the bankruptcy estate by the co-payee. The debtor's
bank normally secures loans to the debtor through a security interest taken
on the debtor's inventory. Joint checks issued by an owner thus will be
considered by the debtor's bank as "cash collateral" arising from the sale
of inventory on which it has a security interest. In this situation, most
courts find that the bank cannot claim a cash collateral security interest
in these proceeds because the funds never become part of the debtor's bankruptcy
estate. First Bulloch Bank & Trust Company v. Inca Materials, Inc.
(Inca Materials, Inc.), 880 F.2d 1307 (11th Cir. 1989).
Problems associated with joint checks can be avoided if they are anticipated
and handled properly when they arise. Joint checks are a useful device
to assure payment is received by the proper parties and is not diverted
for improper purposes. Proper preparation, endorsement, and the use of
allocation instructions will avoid most joint check problems.
.2 Pay-When-Paid Clauses
A "pay when paid" clause provides that the general contractor is not
obligated to pay its subcontractor until some time after the general contractor
has itself been paid by the owner.
Pay-when-paid clauses are enforceable in Georgia. Sasser & Co.
v. Griffin, 133 Ga. App. 83, 210 S.E.2d 34 (1974).
A pay-when-paid clause in a subcontractor's contract may be circumvented
where the court finds that a oral agreement apart from the written contract
supports the claim. Excavators and Erectors, Inc. v. Bullard Engineers,
Inc., 489 F.2d 318 (5th Cir. 1973).
.3 Restrictive Endorsements
An important issue for contractors occurs when the upstream party wishes
to make a partial payment with a restrictive endorsement on the check indicating
something to the effect that the check is "in full and final payment" or
represents "final payment" when in fact the check is for less than the
amount the contractor contends is owed. The Georgia courts treat such a
payment as an "accord and satisfaction." The check is tendered as a "denovo
contract" which is accepted by the other party by cashing the check.
This rule has led to the development of a settlement strategy for resolving
claim disputes with downstream parties known as the "check drop." The strategy
has been used for years by insurance companies who want to settle claims
quickly and who think that the claimant needs or wants the money bad enough
to take less than the full amount of the claim. In a "check drop," the
upstream party issues a check to the downstream party, but the amount of
the check "dropped off" to the downstream party is less than the amount
that the downstream party has claimed, hopes to collect, or believes it
is owed. The check contains a restrictive endorsement, usually indicating
something to the effect that the check is "in full payment of all claims."
This strategy is particularly effective where the downstream party still
owes money to its subcontractors or suppliers which it cannot pay without
payment from the upstream party. Because the check gives the downstream
party some portion of the money it claims that it is due (and at its most
effective, the balance left is not worth the time and legal expense to
fight over) the downstream party may simply sign the check and drop its
claim. If the downstream party signs the check and still presses the claim,
the upstream party claims a release under the previously cited authority.
Where, however, the owner provides the general contractor with numerous
checks, each marked "final payment," and the owner and the general contractor
are engaged in continuing negotiations concerning pending claims, an issue
of fact is created concerning whether the parties had a meeting of the
minds with respect to their intentions in issuing and negotiating these
checks. Dawson Construction Co., Inc. v. Georgia State Financing and
Investment Commission, Ga. Ct. App. Case No. A91A1885 (March 10, 1992).
See
also State Farm Fire & Casualty Co. v. Fordham, 148 Ga.
App. 48(2), 250 S.E.2d 843 (1978).
.4 Submission of Lien Affidavits and Waivers
Construction contracts often contain a condition requiring the submission
of a final lien waiver or an affidavit that all bills for labor and materials
used on the job have been paid as a condition of final payment.
Some courts hold that where a subcontractor has a payment dispute with
the general contractor, no liens had been filed except that of the plaintiff-subcontractor,
and the time for filing liens had expired, then the subcontractor could
not required to waive his lien until he has been paid in full.
.5 Payment Which Is Conditioned on Acceptance
A contract which requires the written acceptance of the contractor's
work as a condition precedent for final payment is enforceable under Georgia
law. D.I. Corbett Electric, Inc. v. Venture Construction Co., 140
Ga. App. 586, 231 S.E.2d 536 (1976); Jerome Distributors, Inc. v. B.L.I.
Construction Co., 142 Ga. App. 776, 237 S.E.2d 13 (1977).
21. Efficiency Claims
Efficiency claims are generally based upon lost productivity caused
by some action of the owner, or for which the owner is responsible. The
efficiency is usually based upon some measure of production which was achieved
by the contractor during the course of construction but which was lost
due to some cost for which the contractor was not responsible. The contractor
sets up an efficiency claim in order to show an entitlement to recover
the difference between cost actually sustained and cost which would have
been sustained had more efficient production been possible.
Lost productivity claims are based upon a variety of factors. Most of
these factors result in a disruption which creates problems in production.
These include out of sequence performance, wherein the contractor is asked
to perform some tasks prior to the time it is most efficiently performed.
Trade stacking is a disruption caused by requiring too many workers or
different work in an area, thereby causing interference between the trades.
Overtime work is a well-established basis for lost efficiency, since many
studies have shown that efficiency falls off during periods of overtime.
In order to succeed in a lost efficiency claim, it is necessary for
the contractor to establish some reasonable baseline for measurement of
efficiency. Such baselines can include previous performance on the current
project, similar performance on other projects, the work of industry trade
groups, national studies of productivity, or expert testimony. There is
virtually no limit to the variety of sources which can be used to establish
lost efficiency, although many of the efficiency measures used are subject
to attack on the grounds that they do not accurately reflect conditions
on the project at issue.
Lost productivity and efficiency claims have been recognized in Georgia
cases, but no extensive analysis of these claims has been conducted by
the Georgia courts. It does seem clear, however, that Georgia courts would
recognize the validity of a lost efficiency claim.
For example, in Georgia Power Company v. Georgia Public Service Commission,
196 Ga. App. 572, 396 S.E.2d 562 (1990), a public utility rate-making case,
the court noted that "productivity" on a construction project is the number
of labor man hours required to install one unit of work. The court observed
that the lower the required number of hours, the more efficient the work
force is and the lower the cost for installing each unit. The court also
recognized "production" as the number of units installed in a given time,
regardless of the man hours required to do the work. Increasing production
is less efficient and more costly, but it can make up time on a schedule.
For example, the court noted that the more people who work on a given task,
the more quickly it normally gets done, even if each person does not work
as efficiently as when that person was working with fewer people. The court
thus clearly recognized the basis for lost efficiency claims in Georgia.
An earlier Georgia case which also seemed to recognize a lost efficiency
claims is Sanford-Brown Company v. Patent Scaffolding Company, Inc.,
1990 Ga. 41 33 S.E.2d 422 (1945). In that case, one of the complaints of
the plaintiff was that the efficiency of the work of its employees who
remained on the job for the plaintiff was reduced by more than 50% due
to a fatal fall caused by rented scaffolds.
22. Delay and Acceleration Claims
.1 In General
Whether a contractor is entitled to a time extension or additional compensation
for a project delay depends upon who or what is responsible for the delay,
and whether this excuses the delay.
Where a contract states that time is of the essence, and the contractor
fails without excuse to timely complete its contractual obligations, then
the contractor is liable for any damages caused by its delay. Heard
v. Dooly County, 101 Ga. 619, 28 S.E. 986 (1897)(weather delays no
excuse); Ladd Lime & Stone Co. v. MacDougald, 32 Ga. App. 709,
124 S.E. 551 (1924)(permitting recovery for cost of idle labor and equipment);
State
Highway Department v. Hall Paving Co., 127 Ga. App. 625, 194 S.E.2d
493 (1972).
Noncompensable delays authorize an extension of the contract completion
date, but do not authorize the collection of damages for the delay. Noncompensable
delays occur when matters outside the control of the parties excuse the
delayed completion.
Compensable delays authorize both an extension of the contract completion
date as well as collection of damages caused by the delay. Compensable
delays occur when one party fails, without excuse, to timely perform a
contractual duty which causes a delay in the other party's performance.
Travelers
Indemnity Co. v. West Georgia National Bank, 387 F. Supp 1090 (N.D.
Ga. 1974)(owner delay in granting contractor's requests for time extensions
estopps owner from recovering liquidated damages); Rome Housing Authority
v. Allied Building Materials, Inc., 182 Ga. App. 233, 355 S.E.2d 747
(1987)(owner's failure to timely issue change order to general contractor);
GYMCO Construction Co., Inc. v. Architectural Glass & Windows, Inc.,
884 F.2d 1362 (11th Cir. 1989)(general contractor's failure to supply template
to subcontractor).
Concurrent delays occur when the actions of both parties cause or contribute
to the delay. In Georgia, neither party may recover damages for a concurrent
delay. J.A. Jones Construction Co. v. Greenbriar Shopping Center,
332 F.Supp. 1336 (N.D. Ga. 1971), aff'd, 461 F.2d 1269 (5th Cir.
1972); Anderson v. Golden, 569 F.Supp. 122 (S.D. Ga. 1982);
Malta
Construction Co. v. Henningson, Durham & Richardson, Inc., 694
F. Supp. 902 (N.D. Ga. 1988)(holding issue is for trier of fact).
Contract language may change this equation by requiring a party to assume
the risk of delays which are caused by factors which are not normally considered
to be within the control of the parties (for example, weather or labor
trouble).
Delay and acceleration on a construction project are related concepts.
Where the contractor is delayed, acceleration may be required in order
to comply with the time requirements of the construction contract unless
a time extension is granted.
Direct acceleration occurs where an order to accelerate performance is given. The contractor normally is entitled to compensation for any extra expense caused by an acceleration order.
Constructive acceleration occurs where either compensable or noncompensable
delays exist, but the contractor's request for an extension of the contract
completion date is refused or deferred. If the contractor accelerates its
performance and incurs additional expense in order to overcome the delay
and achieve the original completion date, then the contractor's performance
has been "constructively" accelerated, even though no direct acceleration
order has been given. The contractor normally is entitled to compensation
for constructive acceleration.
.2 Notice
Where the contract requires the contractor to give notice of any delay
as a condition precedent for recovery of the costs of delay, and the contractor
fails to timely exercise its rights under that provision and apply for
an extension, then the contractor waives its right to a time extension.
Dan-D
v. Burnsed Enterprises, Inc., 188 Ga. App. 207, 372 S.E.2d 303 (1988);
State Highway Department v. Hewitt Contracting Company, 113 Ga.
App. 685, 149 S.E.2d 499 (1966).
Where the notice alerts the opposite party that the claimant has a grievance
against it and reasonably complies with the notice procedure set out in
the contract between the parties, the failure to strictly comply with the
notice procedures is not fatal to the claim. E.C. Ernst, Inc. v. General
Motors Corp., 482 F.2d 1047 (5th Cir. 1973).
.3 Liquidated Damages for Delay.
By statute in Georgia, if the parties agree in their contract to assess
liquidated damages, unless the agreement violates some principle of law,
the parties are bound by this agreement. See O.C.G.A. § 13-6-7.
Gibson
v. Sheriff, 155 Ga. App. 578, 271 S.E.2d 710 (1980).
A liquidated damages provision also limits the owner's recovery to the
amount stated in the liquidated damages provision, nothwithstanding that
larger actual damages were eventually sustained.
Georgia Ports Authority
v. Norair Engineering Corporation, 127 Ga. App. 864, 195 S.E.2d 199
(1973).
On a multiple prime contract, liquidated damages may be assessed against
a contractor who fails to meet milestone dates which result in delays to
the other prime contractors. Georgia Ports Authority v. Norair Engineering
Corporation, 127 Ga. App. 864, 195 S.E.2d 199 (1973).
.4 Waiver or Excuse of Delay Damages.
The fact that adverse weather was encountered does not always excuse contract performance. The contractor should anticipate and make provision in the construction schedule for normal amounts of bad weather. Heard v. Dooly County, 101 Ga. 619, 28 S.E. 986 (1897).
The conduct of the owner may waive the contractual due date, however,
and where evidence of such a waiver exists, summary judgment granting the
owner liquidated damages for the contractor's delay is not warranted. Dan-D
v. Burnsed Enterprises, Inc., 188 Ga. App. 207, 372 S.E.2d 303 (1988).
A subcontractor's delay may be excused by failure of prime contractor
to perform some action which is a constraint on the subcontractor's performance.
Gymco
Construction Co., Inc. v. Architectural Glass & Windows, Inc.,
884 F.2d 1362 (11th Cir. 1989).
.5 Penalty vs. Liquidated Damages
A provision inserted in a contract to deter a party from breaching it
is a penalty and not liquidated damages. The law will enforce liquidated
damages but will not enforce a penalty. To distinguish a penalty from liquidated
damages, a three-part test must be employed. To enforce the provision as
liquidated damages, the court must find:
(1) that the injury caused by the breach is difficult or impossible to estimate accurately;
(2) that the parties intended to provide for damages rather than a penalty;
(3) that the sum stipulated is a reasonable pre-estimate of the probable
loss.
Gibson v. Sheriff, 155 Ga. App. 578, 271 S.E.2d 710 (1980).
OTHER RESOURCES
Annot., Contractual provision for per diem payments for delay in
performance as one for liquidated damages or penalty, 12 A.L.R.4th
891.
.6 No Damage for Delay Clause
A "no damage for delay" clause seeks to prevent the contractor from
recovering for any extra cost associated with suspending or extending the
scheduled or anticipated period of performance for the project. In formulating
its estimate for the cost of the project, the contractor usually estimates
how long the project will take and makes provision for costs accordingly.
If the anticipated completion time of the project is extended, the contractor
might be in the position of having to pay for extended rentals, wage rates
may increase, and project and home office overhead must be carried over
a longer period of time. This obviously increases the contractor's costs.
The Georgia courts have enforced no damage for delay clauses. State
Highway Department v. Wright Contracting Co., 107 Ga. App. 758, 131
S.E.2d 808 (1963). State Highway Department v. MacDougald Construction
Co., 102 Ga. App. 254, 115 S.E.2d 863 (1960).
Perhaps the leading case in our region dealing with the permissible
exceptions to a no damage for delay clauses is E.C. Ernst, Inc. v. Manhattan
Construction Company of Texas, 551 F.2d 1026 (5th Cir. 1977). In that
case, decided under Alabama law, the court noted the harsh effect of "no
damage for delay" clauses and observed that while courts strictly construe
such provisions, they also generally enforce them absent a delay (1) not
contemplated by the parties under the provision, (2) amounting to an abandonment
of the contract, (3) caused by bad faith, or (4) amounting to active interference.
Georgia courts also find that delays which were not contemplated by
the parties provide an exception to enforcement of a no damage for delay
clause. Department of Transportation v. Arapaho Construction Co.,
257 Ga. 269, 357 S.E.2d 593 (1987).
Some courts outside the state of Georgia have held that a contract with
a no damage for delay clause does not preclude the recovery of delay damages
where the contract also contains a provision which requires an extension
of time for completion and the time of completion is not properly extended
in accordance with the requirements of the contract. The courts in these
cases usually state that the enforceability of the no damage for delay
clause is conditioned upon compliance with the extension provisions during
the course of performance under the contract.
OTHER RESOURCES
Annot., "Validity and Construction of 'No Damage' Clause with Respect
to Delay in Construction Contract, 74 A.L.R.3d 187 (1976).
Kovars and Shuham, "'No Damage for Delay' Clauses," Construction Briefings
(Oct. 1987).
TORT CLAIMS
23. Negligence Claims and the "Economic Loss Rule"
Under O.C.G.A. § 51-1-11, no privity of contract is required to
support a tort action. If, however, the tort results from the violation
of a duty arising from a contract, then a different rule applies. In that
event, the right of action is confined to the parties and those in privity
to that contract.
There are express exceptions to this rule for those having a right of
action for the injury which is independent of the contract, and for injured
persons who are third-party beneficiaries of express or implied warranties
under Article 2 of the Uniform Commercial Code. See O.C.G.A. §
11-2-318.
O.C.G.A. § 51-1-11 also carves out another limited exception to
the privity requirement for product liability actions brought by natural
persons who suffer personal injury or property damage from a defective
product.
For the most part, however, absent some representation made in the course
of employment or other duty raised by operation of law, the economic loss
rule bars suits by thrid parties for purely economic losses arising from
the breach of a construction contract.
OTHER RESOURCES
Annot. Recovery for mental anguish or emotional distress, absent independent physical injury, consequent upon breach of contract or warranty in connection with construction of home or other building, 7 A.L.R.4th 1178.
24. Fraud and Misrepresentation Claims
.1 Fraud
The essential allegations of an action for fraud and deceit based on
a promise made in bad faith are (1) that the defendant made representations,
(2) that at the time they were made he knew they were false, (3) that he
made them with the intention and purpose of deceiving the plaintiff, (4)
that the plaintiff relied upon the representations, and (5) that the plaintiff
sustained loss and damages as a proximate result of them having been made.
Cobb
and Eldridge, Ga. Law of Damages § 36-13 at 679 (1989).
.2 Constructive Fraud
Georgia has a complex series of statutes that provide relief for "constructive
fraud." The statutes distinguish actual fraud by stating that it implies
moral guilt, while constructive fraud may be consistent with innocence.
O.C.G.A. § 23-2-51(c).
A misrepresentation of material fact, made willfully to deceive or recklessly
without knowledge and acted upon by the opposite party or made innocently
and mistakenly and acted on by the opposite party, constitutes legal fraud.
O.C.G.A. § 23-2-52.
Likewise, suppression of a material fact which a party is under an obligation
to communicate constitutes fraud. The obligation to communicate may arise
from the confidential relations of the party or from the particular circumstances
of the case. O.C.G.A. § 23-2-53.
Anything which happens without the agency or through fault of the party
affected by it, tending to disturb or confuse this judgment or to mislead
him, of which the opposite party takes an undue advantage, is inequity
as surprised and as a form of fraud for which relief may be granted in
Georgia. O.C.G.A. § 23-2-54.
The courts recognize that fraud may be consummated by signs or tricks,
or through agents employed to deceive, or by any other unfair way used
to cheat another. O.C.G.A. § 23-2-56. Fraud may not be presumed, but
being itself subtle, slight circumstances may be sufficient to prove its
existence. O.C.G.A § 23-2-57.
Confidential relationships may arise from contracts, particularly where
one party is so situated as to exercise a controlling influence over the
will, conduct, and interest of another. Likewise, this relationship of
mutual confidence may arise between partners, principal and agent, and
others. O.C.G.A. § 23-2-58. This provision has been held applicable
to the relationship between an owner and a contractor. Davis v. Carpenter,
247 Ga. 156, 274 S.E.2d 567 (1981).
.3 False Swearing
False Swearing occurs where a person who executes a document knows that
it purports to be an acknowledgment of a lawful oath or affirmation, in
any manner or thing other than a judicial proceeding, and knowingly or
willfully makes a false statement. O.C.G.A. § 16-10-71(a).
The tort of false swearing may arise where an affidavit from an owner is issued indicating that no improvements or repairs have been made to the property within the period during which a lien that could be filed. Peters v. Imperial Cabinet Company, Inc., 189 Ga. App. 337, 375 S.E.2d 635 (1988).
25. Interference with Contractual Relations
Georgia recognizes the tort of intentional interference with contractual
relations. To allege cause of action, a complaint must establish intentional
and improper interference with the performance of the contract. Such an
allegation presumes knowledge of the plaintiff's interest, or at least
of facts that would lead a reasonable person to believe in their existence.
This principle has been applied to a party who destroys the work of
another. Piedmont Cotton Mills, Inc. v. W.H. Ivey Construction Company,
Inc., 109 Ga. App. 876, 137 S.E.2d 528 (1964).
The tort has also been alleged in circumstances where determination
of a contract has been procured by another. Energy Contractors, Inc.
v. Georgia Metal Systems & Engineering, Inc., 186 Ga. App. 475,
367 S.E.2d 324 (1988).
26. Defamation
.1 Slander of Title
Georgia recognizes that the wrongful filing of a mechanic's lien may
give rise to an action for slander of title.
In order to prove such a cause of action, the plaintiff must establish
the elements stated in O.C.G.A. § 51-9-11, which provides that an
owner of an estate in land may maintain an action for libelous or slanderous
words falsely and maliciously impugning his title if any damage shall have
accrued to him therefrom.
The owner must allege and prove the publication of slanderous words
(for example, the wrongful filing of a lien), their falsity, maliciousness,
and special damages. Anderson v. Golden, 569 F. Supp. 122 (S.D.Ga.
1982). See Lincoln Log Homes Marketing, Inc. v. Holbrook,
163 Ga. App. 592, 295 S.E.2d 567 (1982); Carl E. Jones Development,
Inc. v. Wilson, 149 Ga. App. 679, 255 S.E.2d 135 (1979).
Filing a claim of lien against property for materials furnished to the
owner's tenant in an amount exceeding that which the owner agreed to be
liable may be actionable, according to the court in F.S. Associates,
Ltd. v. McMichael's Construction Company, Inc., 197 Ga. App. 705, 399
S.E.2d 479 (1990).
Various defenses to a slander of title action may be asserted by the
lien claimant. For example, pursuant to O.C.G.A. § 51-5-8, the filing
of a lien and a suit to foreclose the lien are privileged. Eurostyle,
Inc. v. Jones, 197 Ga. App. 188, 397 S.E.2d 620 (1990). Privilege also
may be claimed where statements are made in good faith to protect the speaker's
interests. O.C.G.A. § 51-5-7(3).
Matters never before directly addressed by an appellate court also may
create a privilege from slander of title suits. See F.S. Associates,
Ltd. v. McMichael's Construction Company, Inc., 197 Ga. App. 705, 399
S.E.2d 479 (1990).
.2 Damage to Business Reputation
Slander or defamation of business reputation exists when charges against
another are made with reference to his trade, office, or profession, calculated
to injure him. O.C.G.A. § 51-5-4(a)(3).
Defamation of business reputation has been urged in a number of contexts
relating to the construction industry. Dickey v. Brannon, 118 GA.
App. 33, 162 S.E. 2d 827 (1968). (Allegation that one has acted deceitfully
in conducting his business affairs is actionable per se).
27. Contribution and Indemnity
Under Georgia law, any defendant who has been sued may cause a summons
and complaint to be served upon a person not a party to the action who
is or may be liable to him for all or part of the plaintiff's claim against
him. O.C.G.A. § 9-11-14(a).
Parties may be brought in based upon concepts of derivative liability,
including indemnity, subrogation, express or implied warranty, or some
other theory. Insurance Company of North America v. Atlas Supply Company,
121 Ga. App. 1, 172 S.E.2d 632 (1970).
28. Product Liability
.1 Uniform Commercial Code
The Uniform Commercial Code applies to contracts for the sale of goods
and has no application to contracts for services and labor with an incidental
furnishing of equipment and materials. Mingledorff's, Inc. v. Hicks,
133 Ga. App. 27, 209 S.E.2d 661 (1974)(UCC inapplicable to contract for
installation of HVAC system); Dixie Lime & Stone Co. v. Wiggins
Scale Co., 152 Ga. App. 309, 262 S.E.2d 586 (1977)(UCC inapplicable
where there is no allegation that the installed product is defective).
.2 Strict Liability
In 1968, the predecessor statute to O.C.G.A. § 51-1-11 was amended
to abolish the privity of contract defense for actions for breach of implied
warranties in tort against the manufacturer by the injured person. This
statute set the stage for the adoption of the law of product liability
in Georgia.
The Georgia Supreme Court subsequently held manufacturers strictly liable
for damages proximately caused by a defect in a product related to the
product's lack of merchantability and fitness for the use intended. Ellis
v. Rich's, Inc., 233 Ga. 573, 353 S.E.2d 340 (1987); Center Chemical
Co. v. Parzini, 234 Ga. 868, 218 S.E.2d 580 (1975).
This statute also applies to one supplying information or services.
Where one supplies information in the course of his business, profession,
employment, or in any transaction in which he has a pecuniary interest,
he has a duty to use reasonable care and competence in supplying the information
to parties who will rely upon it. In circumstances in which the supplier
of the information was manifestly aware of the use to which the information
was to be put, and intended that it be so used he will have liability limited
to a foreseeable personsor a limited class of persons for whom the information
was intended, either directly or indirectly, where it can be shown that
the representation was made for the purpose of inducing third parties to
rely upon the information and act upon their reliance. Robert &
Co. Assocs. v. Rhodes-Haverty Partnership, 250 Ga. 680, 300 S.E.2d
503 (1983)(site report).
29. Lender Liability
Under a variety of circumstances, lenders have been alleged to be liable
to unpaid contractors, general contractors, and suppliers. See Malloy
v. Planters Warehouse & Lumber Company, Inc., 142 Ga. App. 69,
234 S.E.2d 807 (1977); Williams v. Chatham Real Estate Company,
13 Ga. App. 42, 78 S.E. 869 (1913); Gillis v. B.L.I. Construction Company,
Inc., 148 Ga. App. 527, 251 S.E.2d 800 (1978); First Florida Building
Corporation v. Smith, 530 F. Supp. 496 (N.D.Ga. 1982).
For the most part, such suits have been unsuccessful in Georgia.
Claimants should consider the possibility of requiring lenders to "marshall
assets." See Annot., 76 A.L.R.3d 326 (1977).
Cases in other jurisdictions raise the issue of whether the lender has
a duty, in disbursing funds, to protect the mortgagor against outstanding
or potential liens against the mortgaged property. See Annot., 30
A.L.R.4th 134 (1989).
STATUTORY CLAIMS
30. Prompt Pay Act
.1 Federal (31 U.S.C. § 3901)
The Federal Prompt Pay Act is located at 31 U.S.C. § 3109. Pursuant
to that statute, and certain regulations promulgated by the Office of Management
and Budget, the head of an agency acquiring property or service from a
business concern who does not pay the concern for each complete delivered
item of property or service by the required payment date shall pay an interest
penalty to the concern on the amount of the claim due. This interest penalty
is to be computed at the rate the Secretary of the Treasury establishes
for interest payments under section 12 of the Contract Disputes Act of
1978 (41 U.S.C. § 611). This rate is published in the Federal Register.
31 U.S.C. § 3902.
The regulations promulgated by the Office of Management and Budget require
that, within 15 days after an invoice is received, the head of the agency
notify the business concern of any defect or any impropriety in the invoice
that would prevent the running of the time period specified in the Prompt
Pay Act. 31 U.S.C. § 3903.
Any claim for interest not paid pursuant to the Prompt Pay Act may be
filed as a claim under section 6 of the Contract Disputes Act of 1978.
31 U.S.C. § 3906.
Note that because of a dispute between the head of an agency and a business
concern over the amount of payment or compliance with a contract, an interest
penalty may not be required under the Prompt Pay Act. And all such claims
and interest payable during such period are subject to the Contract Disputes
Act of 1978. 31 U.S.C. § 3906.
.2 State (O.C.G.A. § 13-10-2)
Georgia has its own version of a Prompt Pay Act which is contained in
O.C.G.A. § 13-10-2.
Pursuant to this statute, the state, any county, municipal corporation,
authority, board of education, or other public board, body, department,
agency, instrumentality, or political subdivision of the state must make
at least monthly progress payments based upon the value of the work completed
plus the value of materials and equipment suitably stored, insured and
protected at the construction site.
Retainage under the contract is held to a maximum of 10% of each progress
payment. When 50% of the contract value including change orders and other
additions to the contract is due and the manner of completion of the contract
work and its progress are reasonably satisfactory to the owner or its authorized
contract representative, the owner shall withhold no more retainage. O.C.G.A.
§ 13-10-2(b).
At the discretion of the owner and with the approval of the contractor,
the retainage of each subcontractor may be released separately as the subcontractor
completes his work. O.C.G.A. § 13-10-2(b)(2)(A).
The statute authorizes the owner to resume retention if work of the
contractor becomes unsatisfactory. O.C.G.A. § 13-10-2(b)(2)(B).
At substantial completion, the owner must release the retainage to the
contractor. This must occur within 30 days after the contractor invoices
the retainage, provided that the contract representative determines that
the work is reasonably satisfactory. The statute permits the owner to withhold
200% of the value of any minor, incomplete items. This money is held until
the contract representative determines that these items have been completed.
The statute requires the reduced retainage to be shared by the contractor
and subcontractors as their interest may appear. O.C.G.A. § 13-10-2(b)(C).
Within ten days from the contractor's receipt of retainage from the
owner, the contractor must pass through payments to subcontractors and
shall reduce each subcontractor's retainage in the same manner as the contractor's
retainage is reduced by the owner. The only provisos to this obligation
are that the value of the subcontractor's work complete and in place must
equal 50% of the subcontract value and that the work of the subcontractor
is proceeding satisfactorily, and that the subcontractor has provided reasonable
assurance of continued performance and financial responsibility to complete
his work, including warranty work. O.C.G.A. § 13-10-2(b)(2)(D).
Likewise, the subcontractor must pass through to its own lower tier
subcontractors in the same manner that the general contractor is required
to pass through retainage to him. The same provisos apply to subcontractors.
O.C.G.A. § 13-10-2(b)(2)(E).
This Prompt Pay Act does not apply to contracts let by the Georgia Department
of Transportation for construction, improvement, or maintenance of roads
and highways, nor does it apply to any contract whose value or duration
at the time of the award does not exceed $150,000 or 45 days in duration.
O.C.G.A. § 13-10-2(c).
Any contract or subcontract provisions which are inconsistent with the
benefits extended by this Act are unenforceable. O.C.G.A. § 13-10-2(d).
Nothing contained in the Act precludes a payor from requiring the payee
to submit satisfactory evidence that all payrolls, material bills, and
other indebtedness connected with the work have been paid. O.C.G.A. §
13-10-2(e).
.3 Water and Sewer Contracts
In 1992, the Georgia Legislature enacted O.C.G.A. § 13-10-20, which
is a procedure for retention of contractual payments by the state or its
political subdivisions for the improvement, maintenance, or repair of water
or sewer facilities.
This statute provides that the state and its instrumentalities may not
require retention exceeding 10% of the gross value of the completed work
provided for in a water or sewer contract. Likewise, after 50% of the work
on the project has been completed, retainage may be discontinued. O.C.G.A.
§13-10-20(a).
Retainage must be invested at the current market rate and any interest
earned on the retained amount by such department, agency, or instrumentality
of the state must be paid to the contractor when the project has been completed.
O.C.G.A. § 13-10-20(a).
Final payment of the retained amounts are made after certification by
the engineer that the project has been satisfactorily completed and accepted.
Payment of interest is made after certification by the engineer that the
work was completed within the time specified and within the price specified
within the contract. O.C.G.A. § 13-10-20(b).
At substantial completion of the work, and upon a determination that
the work is reasonably satisfactory, the government must within 30 days
after being invoiced pay retainage to the contractor. The government may
withhold an amount equal to 200% of the value of each incomplete minor
item which is remaining. This sum shall be held until such items are completed
by the contractor.
31. Unfair Business Practices
Georgia has adopted a statute called the "Fair Business Practices Act
of 1975" which prohibits a wide variety of unfair and deceptive practices
in the conduct of any trade or practice. O.C.G.A. § 10-1-390.
The Fair Business Practices Act relates to consumer transactions such
as the sale, purchase, lease, or rental of goods, services, real or personal
property, which are primarily for personal, family, or household purposes.
O.C.G.A. § 10-1-392(a)(3).
Prohibited transactions include representing that goods or services
are of a particular standard or quality, disparaging the goods, services,
or business of another by false or misleading representations, false advertising,
making various types of false statements, and other practices. O.C.G.A.
§ 10-1-393.
The statute authorizes civil penalties, cease and desist orders, and
other relief, including civil and equitable remedies by individuals. The
civil remedies available to individuals include actual and exemplary damages,
as well as the recovery of attorneys' fees. O.C.G.A. § 10-1-399.
32. Antitrust
The anti-trust laws of the United States prohibit any agreements in
restraining of trade. Specific prohibitions include:
Agreeing to fix and regulate prices, mark-ups or the conditions or terms
of a sale;
Agreeing to establish geographic trading areas, allocate markets or
customers, or classify certain customers as being entitled to preferential
treatment;
Participating in any plan designed to induce any manufacturer or distributer
to sell or refrain from selling, or discriminate in favor of or against
any particular customer or class of customer;
Agreeing to limit or restrict the quantity of a product produced;
Participating in any plan designed to control the means of transportation
or channels through which products may be sold; and
Participating in any plan which has the effect of discriminating against
or excluding competitors.
The anti-trust laws of the United States have been asserted in connection
with bid rigging, price fixing and sole source specifications. Parties
injured by anti-trust violations may recover treble damages and other relief.
In addition, criminal prosecution is possible.
33. Bad Faith
Where a defendant acts in bad faith, has been stubbornly litigious,
or has caused the plaintiff unnecessary trouble and expense, Georgia law
permits the plaintiff to plead and recover the expenses of litigation.
O.C.G.A. § 13-6-11.
This statute has been applied on countless occasions in the context
of construction claims. See Gist v. Ferguson Construction Co,,
Inc., 197 Ga. App. 625, 398 S.E.2d 862 (1990); Lineberger v. Williams,
195 Ga. App. 186, 393 S.E.2d 23 (1990); McDonald v. Winn, 194 Ga.
App. 459, 390 S.E.2d 890 (1990); Gunnin v. Parker, 194 Ga. App.
426, 390 S.E.2d 596 (1989); Matthews v. Neal, Greene & Clark,
177 Ga. App. 26, 338 S.E.2d 496 (1985);
Jackson v. Brinegar, Inc.,
165 Ga. App. 432, 301 S.E.2d 493 (1983); Ideal Pool Corp. v. Champion,
157 Ga. App. 380, 277 S.E.2d 753 (1981); Georgia-Carolina Brick &
Co. v. Brown, 153 Ga. App. 747, 266 S.E.2d 531 (1980).
PROVING DAMAGES
34. Pricing Claims
.1 Pricing Methods
There are several methods of pricing construction claims. Each of these
methods may be acceptable, depending upon the facts and circumstances of
each case.
The preferred method for pricing construction claims is the "actual
cost" method. This method uses actual cost of the labor and material expended,
as reflected in the records of the contractor. Ideally, the contractor
will establish a cost code for the labor and material expended as a result
of the claim, so as to permit the final job cost report for the project
to reflect the actual cost of the claim.
A second method for pricing construction claims is the "total cost method."
This is one of the most common methods of pricing a construction claim,
because it is the easiest method. This method uses the "as planned" expenditures
for the project and compares them to the "as built" expenditures for the
project. The difference between the two is the amount of the claim.
While this method of pricing the claim has the virtue of simplicity,
the primary problem with the total cost method is that it assumes that
the contractor's estimate is completely accurate and attributes all extra
costs experienced by the contractor to the claim. The total cost method
ignores any added costs which were the responsibility of the contractor.
For example, some project costs may be higher than planned due to the estimating
or construction errors, as well as many other problems which obviously
were not caused by the owner. For this reason, the total cost approach
should only be used where no other method of pricing the claim is available.
A third method of pricing the claim is called the "modified total cost
method." This method also uses the difference between the "as planned"
versus "as built" cost of the project as the basis for the claim, but adjustments
are made in the claim to account for any other factors which might have
increased the cost of construction. By subtracting all of the other possible
costs which are not attributable to the owner, and validating the original
estimate, the contractor considerably increases the credibility of the
claim.
Regardless of the method used to price the claim, the contractor should
accurately attempt to price the claim without inflating or distorting the
value of the claim. If the contractor uses higher overhead and profit figures
in the claim than were used in the initial estimate, then the contractor
should be prepared to explain why those figures are justified.
It also goes without saying that if the contract sets out a method and
procedure for pricing the claim, this method should be followed by the
contractor, if possible. Most standard form contracts now provide several
methods for pricing claims, including mutual agreement on a fixed price,
unit pricing, or time and materials billings.
The contractor should remember to include any time extensions or schedule
impacts caused by the claim.
.2 Lost Profits
Georgia follows the general rule that bars the recovery of lost profits
which are remote or speculative. In order to overcome this obstacle, the
courts usually will require evidence of lost orders or contracts which
could not be filled. Developing evidence of prospective profits may be
difficult or impossible where the claimant is operating a new business
which is not yet profitable.
.3 Consequential Damages
The contractor should consider including within the claim any consequential
damages which flow from the breach of contract, such as lost bonding capacity.
Such damages must have been within the contemplation of the parties at
the time of the breach in order to be recovered. The best way to assure
that this standard is met is to notify the owner in writing of any consequential
damages which will be encountered as a result of the claim.
.4 Field and Home Office Overhead
The Georgia courts have not recognized the Eichleay or Capital
Electric line of cases which recognize that the contractor is entitled
to recover that portion of extended home office and field overhead arising
from any delay on the project.
35. Interest
O.C.G.A. § 7-4-15 permits the recovery of prejudgment interest
on all liquidated demands where "the sum to be paid is fixed and certain."
Such a claim bears interest from the time the debtor becomes "liable and
bound to pay."
Where an interest rate is not established by written contract, a lien
claimant may recover simple interest at the legal rate of 7% per annum.
Horkan
v. Great American Indemnity Company, 211 Ga. 690, 88 S.E.2d 13 (1955).
See O.C.G.A. § 7-4-2(a)(1)(A).
Interest at the higher rate of 1.5% per month, as set out in O.C.G.A.
§ 7-4-16, is permitted for unpaid debts on commercial accounts. Where,
however, the defendant is not an account debtor of the lien claimant, then
interest may be recovered against that defendant only at the legal rate
of 7% per annum simple interest, and not at the higher rate set out in
O.C.G.A. § 7-4-16. Turner Construction Company v. Electrical Distributors,
Inc., Case No. A91A1932 (Ga. Ct. App., Feb. 7, 1992).
Interest may not be claimed on the amount of the lien where there is no agreement or judgment fixing the principal amount as liquidated. Cowart v. Reeves, 80 Ga. App. 161, 55 S.E.2d 911 (1949).
Where the claim is liquidated, however, it bears interest from the time
the party becomes liable and bound to pay it. Carmichael Tile Co. v.
National Surety Co., 166 Ga. 709, 144 S.E. 250 (1928). A debt is liquidated
when it is certain how much is due and when it is due. Sunderland v.
Vertex Associates, Inc., 199 Ga. App. 278, 404 S.E.2d 574 (1991).
A plaintiff may recover prejudgment interest at the legal rate from
the date of breach, even on an unliquidated claim. O.C.G.A. § 13-6-13.
The Georgia courts have permitted the recovery of interest on lien claims
from the date of maturity of the lien claim. David v. Marbut-Williams
Lumber Co., 32 Ga. App. 157, 122 S.E.906 (1924).
After a judgment is obtained, the claimant may recover interest at the
rate of 12% per annum, or another rate is specified in the contract or
obligation. O.C.G.A. § 7-4-12.
36. Attorneys' Fees
.1 In General
In Georgia, attorneys' fees are recoverable only when authorized by
statute or by contract. City of Lawrenceville v. Heard, 194 Ga.
App. 580, 391 S.E.2d 441 (1990). The recovery of attorneys' fees is authorized
from a wide variety of statutory sources.
Attorneys' fees may be recovered for bad faith, stubbornly litigious conduct, or causing the plaintiff unnecessary trouble or expense, pursuant to O.C.G.A. § 13-6-11. Ballenger Corporation v. Dresco Mechanical Contractors, Inc., 156 Ga. App. 425, 274 S.E.2d 786 (1980)(bad faith); Khoury v. Skidaway Island Engineering, Inc., 172 Ga. App. 503, 323 S.E.2d 692 (1984)("stonewalling" in the absence of a bona fide controversy causes "unnecessary trouble and expense").
Note that the defendant may seek attorneys' fees under O.C.G.A. §
13-6-11 only if it has an independent cause of action asserted against
the plaintiff in a counterclaim. In other words, a counterclaim for collection
of attorneys' fees cannot be filed against the plaintiff merely because
the plaintiff sued the defendant. Ballenger Corporation v. Dresco Mechanical
Contractors, Inc., 156 Ga. App. 425, 274 S.E.2d 786 (1980).
Pursuant to O.C.G.A. § 51-7-80, etseq., a claim for reasonable
attorneys' fees and the expenses of litigation is available to punish or
deter abusive litigation. Such claims must be brought after giving due
and proper statutory notice, and within 45 days after the final disposition
of the underlying action.
Georgia has the equivalent of the federal "Rule 11" sanctions in O.C.G.A.
§ 9-15-14, which provides for the assessment of attorneys' fees against
a party who asserts a "claim, defense, or other such position with respect
to which there existed such a complete absence of any justiciable issue
of law or fact that it could not be reasonably believed that a court would
accept the asserted claim, defense, or other position."
The taking of a frivolous appeal also permits the recovery of a penalty,
pursuant to O.C.G.A. § 5-6-6. Ayers v. Advertising Concepts,
169 Ga. App. 400, 312 S.E.2d 876 (1984).
.2 Attorneys' Fees in Arbitration
Attorneys' fees may be awarded in arbitration proceedings if the underlying
contract provides that the prevailing party is entitled to recover attorneys'
fees. Hope & Associates, Inc. v. Marvin M. Black Co., Ga. Ct.
App. Case No. A92A1096 (Sept. 24, 1992).
This issue previously had been in some doubt due to two cases interpreting
O.C.G.A. § 9-9-17 (formerly codified as O.C.G.A. § 9-9-97(a)).
The court overruled Walton Acoustics, Inc. v. Currahee Construction
Co., Inc., 197 Ga. App. 659, 399 S.E.2d 265 (1990) and Hughes &
Peden v. Budd Contracting Co., 193 Ga. App. 656, 388 S.E.2d 753 (1989),
both of which had held that the allowance of attorneys' fees in arbitration
was improper under this statute.
37. Statutory Penalties
.1 Insurance
Georgia has a bad faith statute applicable to insurance companies. Under
the provisions of O.C.G.A. § 33-4-6, in the event of a loss which
is covered by a policy of insurance and the refusal of the insurer to pay
the same within 60 days after a demand has been made by the holder of the
policy and a finding has been made that such refusal was in bad faith,
the insurer is liable to pay the insured, in addition to the loss, up to
25% of the liability of the insurer for the loss and all reasonable attorneys'
fees for the prosecution of the action against the insurer.
Filing a proof of loss is not equivalent to a demand for payment under
this Code section. Guarantee Reserve Ins. Co. v. Norris, 219 Ga.
573, 134 S.E.2d 774 (1964).
To recover attorneys' fees or a penalty for bad faith, a demand for
payment of the loss must be made more than 60 days prior to the filing
of the suit. Hanover Ins. Co. v. Hallford, 127 Ga. App. 322, 193
S.E.2d 235 (1972).
.2 Surety
Georgia has a bad faith statute applicable to compensated sureties.
Under the provisions of O.C.G.A. § 10-7-30, the refusal of the corporate
surety to commence the remedy of a default covered by its bond and to make
payment to an obligee under the terms of the bond within 60 days after
receive of a notice of default, can subject the surety to liability for
a 25% penalty and reasonable attorney's fees for the prosecution of the
case against the surety. The application of this section is in derogation
of the common law and must be strictly construed. Traveler's Indemnity
Company v. Sasser & Company, 138 Ga. App. 361, 226 S.E.2d 121 (1976).
One of the most common failings of the surety is its failure to investigate
all of the facts and circumstances surrounding the alleged default by the
principal. Where there is an allegation that the principal has defaulted,
the surety should exercise reasonable diligence in investigating the facts
and circumstances of the default, and should make an independent determination
of the liability of its principal.
Often, the surety relies upon the efforts of the principal to investigate
the claim. Such a delegation of the surety's duty to investigate could
raise questions about this efficiency of the surety's investigation, particularly
where it is in the principal's interest to convince the surety that the
principal is not in default.
Failure to wait at least 60 days after making demand for payment before
filing suit constitutes an absolute bar to the statutory claim for a bad-faith
penalty and attorneys fees. Columbus Fire & Safety Equipment Co.
v. American Druggist Insurance Co., Inc., 166 Ga. App. 509, 304 S.E.2d
471 (1983).
The provisions of this penalty statute have been held applicable to
compensated sureties.
38. Punitive Damages
By statute in Georgia, unless otherwise provided by law, exemplary damages
shall never be allowed in cases arising on contracts. O.C.G.A. § 13-6-10.
Where the breach of contract action is joined with a tort action, such as fraud, then punitive damages may be recoverable in the tort action.
CONSTRUCTION CLAIM DEFENSES
39. Statutes of Limitation and Repose
The statute of limitations for a suit to recover damages for injury to reputation is one year. O.C.G.A. § 9-3-33.
The statute of limitations for a suit for personal injuries is two years.
O.C.G.A. § 9-3-33.
The statute of limitations for a suit to recover for damage to real
property is four years. O.C.G.A. § 9-3-30.
The statute of limitations for a suit to recover for damage to personal
property is is four years. O.C.G.A. § 9-3-31.
The statute of limitations for a suit on an oral contract is four years.
O.C.G.A. § 9-3-26.
The statute of limitations for a suit on a written contract is six years.
O.C.G.A. § 9-3-34.
The statute of limitations for a suit on a contract under seal is twenty
years. O.C.G.A. § 9-3-23.
The fact that the damage was not discovered is no defense to the running
of the statute of limitations. Corporation of Mercer University v. Gypsum
Company, 258 Ga. 365, 368 S.E.2d 732 (1988). The
Mercer case
overruled Lumberman's Mutual Casualty Co. v. Patillo Construction Co.,
Inc., 254 Ga. 461, 330 S.E.2d 344 (1985), which had held that the "discovery
rule" applied in Georgia.
Where a defendant fraudulently prevents a potential plaintiff from learning
of the existence of a claim, this fraud tolls the statute of limitations.
O.C.G.A. § 9-3-96.
Georgia also has a statute of repose which states that all causes of
action arising from the design or construction of a building must be brought
within eight years after substantial completion of the work. O.C.G.A. §9-3-51.
40. Waiver/Estoppel
.1 In General
Waiver is the conscious relinquishment of a known right.
Estoppel arises where a party, by its conduct, causes another party
to act or prevents another party from acting to its detriment.
.2 Making or Accepting Final Payment
Waiver issues frequently arise in the context of final punchout of the
project. Contractors frequently claim that the owner's final payment constitutes
an express or implied waiver of any other or further claims against the
general contractor, or acceptance of the work "as is" by the owner. A number
of the standard-form contracts commonly used in the construction industry
contain clauses which also may affect the continued viability of certain
claims after final payment by the owner.
Receipt of final payment alone does not constitute an accord and satisfaction.
Landon
v. Lavietes, 156 Ga.App. 123, 274 S.E.2d 120 (1980); Puppy Love
Kennel, Inc. v. Norton, 158 Ga. App. 69, 279 S.E.2d 213 (1981).
.3 Acceptance of Construction
The simple occupancy of the building by the owner does not waive the
owner's right to hold the contractor responsible for construction defects,
particularly where the final accounting for the project has not been completed.
Cannon
v. Hunt, 116 Ga. 452, 42 S.E. 734 (1902).
Failure to call upon the contractor to repair defects, and acceptance
and use of the building without complaint by the owner, are tacit recognition
by the owner of completion of the contract and of the obligation of the
owner to pay the contractor. Porter v. Wilder & Son, 62 Ga.
520 (1879).
.4 Continued Performance After Breach
Continued performance of a contract after a material breach of the contract
by the opposite party may waive the right to terminate the contract for
this breach, but not the right to collect damages for the breach. Gymco
Construction Co., Inc. v. Architectural Glass & Windows, Inc.,
884 F.2d 1362 (11th Cir. 1989).
.5 Failure to Act
The owner's delay in granting contractor's requests for time extensions
may estopp an owner from recovering liquidated damages. Travelers Indemnity
Co. v. West Georgia National Bank, 387 F. Supp. 1090 (N.D. Ga. 1974).
OTHER RESOURCES
J. Sweet, Completion, Acceptance and Waiver of Claims: Back to Basics,
17 Forum 1312 (1982).
41. Hold Harmless and Indemnity Clauses
Hold harmless and indemnity clauses are extremely common in the construction
industry. They are an acceptable means of allocating the risk of loss from
one party to another, provided that both parties understand the risk which
has been allocated and the responsibilities attendant to that allocation
of risk.
Georgia law prohibits the enforcement of an indemnity provision in a
construction contract which attempts to provide indemnity for the sole
negligence of the party indemnified. Such contracts are considered void
as against public policy. O.C.G.A. § 13-8-2(b).
Such contract provisions have been construed as requiring the indemnifying party to provide insurance for the benefit of the indemnified party. Tuxedo Plumbing and Heating Company, Inc.v Lie-Nielsen, 245 Ga. App. 27, 262 SE2d 794 (1980);
42. Performance Defenses
.1 Impossibility
If performance becomes impossible by an act of God, or from some act or fault of the other party, such impossibility excuses performance. O.C.G.A. § 1-3-3(3).
If performance of the terms of a contract become impossible as a result
of an act of God, such impossibility shall excuse nonperformance except
where by proper prudence such impossibility might have been avoided by
the promisor. O.C.G.A. § 13-4-21.
Acts of God include any accident produced by physical causes which are
irresistible, such as lightening, storms, perils of sea, earthquakes, inundations,
sudden death or illness. Acts of God exclude "all idea of human agency."
Cannon
v. Hunt, 113 Ga. App. 501, 38 S.E. 983 (1901).
.2 Commercial Impracticability
The courts in Georgia rejected the defense of "economic impossibility"
in
Jerome Bradford Construction Co., Inc. v. Pinkerton & Laws Co.,
174 Ga. App. 854, 332 S.E.2d 26 (1985), finding that where the contractor
is aware of the requirements of the contract and the contract imposes no
duty on the general contractor to allow for a change, the mere fact that
the job proves to be more difficult than anticipated does not form the
basis for any legal relief.
The Georgia courts have frequently held that a contractor performing
work under a fixed price contract is not entitled to additional compensation
merely because unforeseen difficulties causing additional expense are encountered
in the performance of the contract. This is particularly true where the
contractor knowingly assumes the risk of performance in the contract. Decatur
County v. Praytor, Houston & Wood, 165 Ga. 742, 142 S.E.2d 678
(1928).
The Georgia courts have even rejected this form of relief even where
the conditions were unknown by either party to the contract. Anderson
v. Golden, 569 F.Supp. 122 (S.D. Ga. 1982)(subcontractor assumed risk
of soil conditions).
.3 Non-Performance by Opposite Party (O.C.G.A. § 13-4-23)
Georgia law provides that non-performance by the opposite party excuses
the other party from performance. O.C.G.A. § 13-4-23.
.4 Substantial Compliance
(O.C.G.A. § 13-4-20)
Georgia law provides that performance must be substantially in compliance
with the spirit and the letter of a contract, and must be completed within
a reasonable time. O.C.G.A. § 13-4-28.
43. Mistake
.1 Reformation for Mutual Mistake
Reformation is available in Georgia only in cases of mutual mistake.
O.C.G.A. § 23-2-31.
In Georgia, mutual ignorance of fact (i.e., lack of knowledge
of some fact) does not afford a basis for equitable relief from
the contract. See O.C.G.A. § 23-2-28. Mutual ignorance of fact
is not considered the equivalent of a mutual
mistake of fact under
Georgia law.
.2 Rescission for Unilateral Mistake
"Unilateral" mistakes of fact include mistakes such as mathematical
or clerical errors, omission of bid items, erroneous assumptions, factual
misunderstandings or misinterpretations. Where a bid error of this type
occurs, contractors are often given relief from their bid mistake.
Other types of unilateral mistakes go to the judgment of the contractor
in submitting its bid. These mistakes include erroneous estimates of the
time to complete the project or the crews or equipment needed.
Likewise, unilateral mistakes caused by mere ignorance of the facts
or of the legal or statutory requirements of the contract, normally do
not form the basis for legal relief. In the absence of fraud, artifice,
or deception, it is difficult to secure relief for these types of mistakes
in Georgia. O.C.G.A. §§ 23-2-27, 23-2-29.
The remedy of cancellation or "recission" of the contract is available
for unilateral mistakes. See O.C.G.A. § 23-2-31.
.3 Duty to Investigate
Under Georgia law, relief from mistakes of fact may only be obtained
if the complaining party applies for relief within a reasonable time. O.C.G.A.
§ 23-2-24.
In the absence of fraud, misplaced confidence, or some other misrepresentation,
if a contractor though the exercise of reasonable diligence could have
determined the true facts then equitable relief is not available. O.C.G.A.
§ 23-2-29.
44. Non-Resident Contractors Act
Georgia law requires every construction contractor who is a non-resident
of the state of Georgia to register pursuant to the Georgia Non-Resident
Contractors Act, O.C.G.A. § 48-13-32.
Non-resident contractors who fail to register in accordance with the
Act are barred from maintaining an action to recover payment for performance
on the contract in the courts of the state of Georgia. O.C.G.A. §
48-13-37. See Lenox Hotel Company v. Charter Builders, Inc.,
717 F. Supp. 1558 (N.D.Ga. 1989).
Substantial compliance with the statute is sufficient. D.O.T. v.
Moseman Construction Company, 260 Ga. 369, 393 S.E.2d 258 (1990).
If a suit is dismissed under the Non-Resident Contractors Act, it is
dismissed without prejudice to refiling. Clover Cable of Ohio, Inc.
v. Heywood, 260 Ga. 341, 392 S.E.2d 855 (1990).
45. Agency
It is extremely important for the contractor to know the authority of
those who the contractor deals with every day on a project. Where a contract
set out that the owner may act only through a designated project representative,
the contractor should obtain interepreation of plans and specifications
or authorization to perform extra work only from this representative.
Where an agent of the owner authorizes the performance of extra work
in writing, but the owner subsequently denies liability for the extra work,
a jury issue is presented as to whether the agent had authority to order
the work on behalf of the owner. Highsmith v. National Linen Service
Corp., 63 Ga. App. 112, 10 S.E.2d 237 (1940).
In Gymco Construction Co., Inc. v. Architectural Glass & Windows,
Inc., 884 F.2d 1362 (11th Cir. 1989), an on-site representative was
held not to have authority to make changes in contracts; a written change
order should have been obtained.
46. Sovereign Immunity
Pursuant to the Georgia State Constitution, Article I, § II, ¶
IX, the State of Georgia has sovereign immunity immunizing it from suit
for its actions and the actions of all of its departments and agencies.
Sovereign immunity can only be waived by an act of the general assembly
which specifically provides that sovereign immunity is waived and provides
for the extent of such waiver.
The general assembly has enacted many waivers of sovereign immunity.
Officers and employees of the state and all its departments and agencies
are subject to suit and may be liable for injuries or damages caused by
the negligent performance of, or negligent failure to perform, their ministerial
functions. They also may be liable for injuries and damages if they act
with actual malice or with actual intent to cause injury in the performance
of their official functions. Georgia Constitution, Article I, § II,
¶ IX(d).
The defense of sovereign immunity is waived as to any contract action
arising from the breach of a written contract with the State of Georgia,
its departments, agencies and authorities, and suit may be filed on such
actions in the Superior Court of Fulton County as well as any other location
where venue would otherwise be present. O.C.G.A. § 50-21-1.
47. Failure of Consideration
Any condition precedent or subsequent not complied with, including insufficiency
or failure of consideration, or any act of the opposite party by which
the obligation of the contract has ceased, may be pleaded as a defense
in Georgia. O.C.G.A. § 13-5-8.
Specifically, if the consideration for a promise, apparently good or
valuable, fails either wholly or in part before the promise is executed,
the failure of consideration may be pleaded in defense to the promises.
O.C.G.A. § 13-5-9.
Failure of consideration is an affirmative defense which must be especially
pled in Georgia. O.C.G.A. § 9-11-8(c).
If the failure of consideration is only partial, an apportionment shall
be made according to the facts of each case. O.C.G.A. § 13-5-9.
A defense of failure of consideration is often pled as a defense to
defective construction. The proof must substantiate to what the extent
the consideration has failed so that it will be possible for the jury or
the court to determine the extent of the failure of consideration. Absence
of such proof, the defense of partial consideration must fail. Anchor
Sign Company of Georgia, Inc. v. PS Heating & Air Conditioning Company,
125 Ga. App. 207, 186 S.E.d 892 (1971).
48. Accord & Satisfaction
An accord and satisfaction occurs where the parties to an agreement,
by some subsequent agreement, have satisfied the former agreement, and
the latter agreement has been executed. The execution of a new agreement
may itself amount to a satisfaction of the former agreement where it is
so expressly agreed by the parties. Without such an agreement, if the new
premise if founded on a new consideration, the taking of it is a satisfaction
of the former agreement. O.C.G.A. § 13-4-101.
A creditor's agreement to receive less than the amount of its debt cannot
be pleaded as an accord and satisfaction unless it is actually executed
by the payment of money, the giving of additional security, the substitution
of another debtor or some other new consideration. O.C.G.A. § 13-4-103(a).
Accord and satisfaction is often argued when a check is tendered, marked "payment in full." An accord and satisfaction by such a payment does not exist unless a bonafide dispute or controversy exists to the amount due and such payment is made pursuant to an independent agreement between the creditor and the debtor that such payment shall satisfy the debt. O.C.G.A. § 13-4-103(b).
Where an accord and satisfaction exists, however, it is binding upon both of the parties to the agreement. O.C.G.A. § 4-104.
49. Novation
Any change in the nature or terms of a contract can create a novation.
A novation has four essential elements:
(1) a previously valid obligation,
(2) the agreement of all of the parties to a new contract,
(3) the extinguishment of the old contract, and
(4) the validity of the new contract.
The concept of novation is important in construction claims, particularly
as it may apply to the allegations of a surety. For example, a novation
of an underlying obligation was bonded by the surety, without the consent
of the surety, discharges the surety. O.C.G.A. § 10-7-21.
Novations may be waived by the provisions of the bond stating that any
change in the underlying contract does not require a notice to the surety.
In Georgia, compensated sureties are not afforded the same level of
protection as uncompensated sureties. For this reason, a compensated surety
may not be able to take advantage of a novation defense.
One way of avoiding the novation defense is to make sure that any new
agreement entered into by the parties expressly states that it does not
extinguish any previous contracts between the parties. This will prevent
the extinguishment of the old contract and will eliminate one of the essential
elements of a novation.
50. Set Offs
After a breach of contract, no contractual relationship continues to
exist. Where a subcontractor, for example, fails to complete a project
and therefore breaches a contract with the general contractor, the general
contractor is entitled to set off the amount of the incomplete work for
any amounts owing to the subcontractor. Simonton Construction Company
v. Pope, 213 Ga. 360, 99 S.E.2d 216 (1957).
51. Insurance
Insurance policies provide an avenue for recovery of many construction
claims.
One of the most important policies is the contractor's comprehensive
general liability insurance policy. The typical CGL policy provides coverage
for premises and operations liability, elevator liability and independent
contractor's protective liability. This policy is now frequently called
a "commercial" general liability policy.
A second important category of insurance is builders risk insurance.
This policy provides both property damage protection and liability coverage.
Usually the contractor will have the opportunity to select various "endorsements"
which can add additional protection to the builders risk policy. If the
project is damaged during the course of construction, the contractor's
builders risk insurance may provide coverage to reimburse the contractor
for this loss.
Workers compensation insurance is required by law in Georgia. If a subcontractor
does not obtain workers compensation insurance for its employees, then
the general contractor may be liable under its own policy for injuries
to these employees. O.C.G.A. § 34-9-8.
Regardless of the type of insurance involved, several general practices
and procedures should be followed in making a claim. First, the claim should
be presented as soon as possible to the carrier, and in as much detail
as possible. Although contacting the insured by telephone is adequate to
place the insurer on notice, the telephone notice should be followed by
written notice confirming the telephone call.
Second, demand for payment should be made immediately. The mere filing
and submission of a claim does not constitute a demand for payment of the
claim. It is helpful to send a demand for payment of any proof of claim
which is submitted to an insurance company. The letter should clearly state
that payment of the claim is demanded immediately and instruction should
be given for how the check is to be made out by the insurer.
Third, it should always be remembered that insurance companies have
subrogation rights which permit them to recover losses paid out to their
insureds. Most policies prohibit any action by the insured which imperils
the subrogation rights of the insurance company. Accordingly, a contractor
should carefully consider the implications of signing any release which
has the affect of releasing a party causing damage to the contractor. For
example, if a subcontractor starts a fire which damages the general contractor's
work, the general contractor may recover for these losses from its insurance
company. The insurance company will then attempt to recoup this payment
from the subcontractor who caused the fire. If, in the interim, the general
contractor has signed a release of the party at fault, perhaps after having
received some payment from the defendant, then the insurance company for
the contractor may be precluded from making this recovery. This may be
a violation of the policy and the general contractor may be held liable
for its failure to protect the subrogation interest of the insurance company.
DISPUTE RESOLUTION
52. Arbitration
1. In General
In deciding whether to insert an arbitration clause in a construction
contract, a number of advantages and disadvantages should be considered.
The arbitration will be conducted before a panel of experts selected
by the parties from a list maintained by the AAA. These experts know the
construction industry and are familiar with its special problems and challenges.
By the same token, these experts bring with them their own point of
view on many matters. It may be difficult for an arbitrator to be neutral
about matters with which they have great personal familiarity.
Although the arbitration process has its own delays, an arbitration
decision usually can be obtained much faster than a court decision, usually
within a matter of a few months from the selection of the arbitrators.
Fees for arbitration are based on the amount in controversy and can
be quite high if the amounts in controversy are large. Fees usually must
be paid in advance and may not be fully refunded even if the arbitration
does not go forward.
Unless a neutral site can be agreed upon, the AAA will usually hold
the arbitration hearing in its offices. A fee may be charged for use of
the arbitration room, particularly if the hearing extends over several
days.
The arbitrators must be paid by the parties. The first arbitration hearing
is free, but this free day may be taken up with a prehearing conference.
Thereafter, the arbitrators are compensated by a daily fee which can amount
to thousands of dollars over a lengthy hearing. The arbitrators' expenses
(hotel, food, transportation, etc.) are all billed to the parties.
These fees and expenses may be allocated by the arbitrators to the losing
party, or it can be split between the parties, as the arbitrators see fit.
There is no discovery in arbitration, except for that ordered by the
arbitrators or agreed to by the parties. Usually, only exhibits which will
be introduced in evidence at the arbitration are exchanged by the parties.
The parties save the cost of conducting discovery. This reduces preparation
costs, but it may lengthen the time of the arbitration hearing.
The lack of discovery also means that neither side has much possibility
of learning about the other side's case prior to the hearing. This means
that a party has less chance of learning the relative strengths and weaknesses
of each side's case. This may reduce settlement opportunities and increase
the chance of unpleasant surprises at the hearing.
Arbitration is a contractual dispute resolution process. This means
that only those parties who contractually agree to arbitrate can be joined
in the arbitration. Architects and engineers usually have provisions in
their contracts barring them from being joined in any arbitration between
the owner and the contractor. This usually requires them to be sued in
a separate action.
In arbitration, the hearing can and often is broken up into segments.
This can be more convenient than a court case, where the judge directs
the attorneys to appear at trial and to conduct the trial through to a
conclusion, usually with no adjournment. The downside of this is that evidence
presented at the first arbitration hearing may be forgotten by the time
the last hearing is held.
Scheduling a hearing can be a problem in arbitration. Usually, the panel
is made up of professionals who have busy schedules. It often is difficult
to find a block of time that is convenient for everyone. This can result
in a considerable delay in holding the first hearing, and may require a
month or more between hearings if the hearing is broken up into segments.
There is virtually no possibility of reversing an arbitration award
on appeal. In the absence of fraud or misconduct, the decision of the arbitrators
is final. This is fine if you win, but what happens if you lose?
2. Georgia Arbitration Code
(O.C.G.A. § 9-9-1)
Georgia has adopted an arbitration statute called the Georgia Arbitration
Code. O.C.G.A. § 9-9-1.
The Georgia Arbitration Code applies to all disputes in which the parties
have agreed in writing to arbitrate and "shall provide the exclusive means
by which agreements to arbitrate disputes can be enforced" in Georgia,
with certain stated exceptions. O.C.G.A. § 9-9-2.
An arbitration agreement submitting the controversy to arbitration or
a contract which provides for arbitration of disputes arising under the
contract is enforceable pursuant to the Georgia Arbitration Code. O.C.G.A.
§ 9-9-3.
Under the Georgia Arbitration Code, demand for arbitration must be served
on the other parties to the arbitration by registered or certified mail,
return receipt requested. This statute provides for preliminary injunctions,
attachment, and other special relief upon application to a court having
jurisdiction of the controversy. O.C.G.A. § 9-9-4.
If a party seeks to arbitrate a claim which would be barred by a statute
of limitation had the claim been asserted in court, a party is authorized
under the Georgia Arbitration Code to apply for a stay of the arbitration
or vacate any award rendered by the arbitrators. A party waives the right
to raise the limitation of time as a bar to arbitration in an application
to stay arbitration by that party's participation in the arbitration. O.C.G.A.
§ 9-9-5.
An application to compel arbitration may be filed with a court having
jurisdiction. A party also may apply to stay arbitration if no valid agreement
to submit to arbitration was made, if the arbitration agreement was not
complied with, or if the arbitration is barred by a limitation of time.
O.C.G.A. § 9-9-6.
Where a party serves a demand for arbitration, the demand must specify
the agreement pursuant to which the arbitration is sought, the name and
address of the party serving the demand, that the party served with the
demand shall be precluded from denying the validity of the agreement or
compliance therewith or from asserting the limitation of time as a bar
in court unless he makes application to the court within 30 days for an
order to stay arbitration, and the nature of the dispute or controversy
sought to be arbitrated. Amendments are permitted after the original demand
is served. O.C.G.A. § 9-9-6.
After service of the demand for arbitration or any amendment thereto,
the parties served must make application within 30 days to the court for
a stay of arbitration or be precluded from denying the validity of the
agreement to arbitrate. The right to apply for a stay of arbitration may
not be waived except as set out in the Georgia Arbitration Code. O.C.G.A.
§ 9-9-6.
Parties may seek consolidation of separate arbitration proceedings under
certain circumstances. O.C.G.A. § 9-9-6(e).
The Georgia Arbitration Code provides that if an arbitration agreement
sets out a method for appointment of arbitrators, that method shall be
followed. If there is no method set out in the agreement or if for some
reason the method fails or is not followed then the court may appoint one
or more arbitrators on application of a party. O.C.G.A. § 9-9-7.
Arbitrators shall appoint the time and place for a hearing and may overrule
the designation of the place of hearing stated in the arbitration agreement.
Ten days' notice is required before the hearing is held. The arbitrators
may adjourn or postpone the hearing. A court may direct the arbitrators
to proceed promptly with the hearing in a determination of the controversy.
O.C.G.A. § 9-9-8(a).
At the arbitration, the parties are entitled to be heard and to present
pleadings, documents, testimony and other matters including cross-examination
of witnesses. Parties have the right to be represented by an attorney.
The hearing must be conducted before all the arbitrators unless the parties
agree otherwise. A majority of the arbitrators may determine any question
and render or change any award. The arbitrators are required to maintain
a record of all pleadings, documents, testimony and other matters introduced
at the hearing, including ordering the proceedings to be transcribed by
a court reporter. O.C.G.A. § 9-9-8.
The arbitrators may issue subpoenas for the attendance of witnesses
and for the production of books, records, documents, and other evidence.
The subpoenas may be served by the court and enforced in the same manner
as service and enforcement of subpoenas in a civil action. Discovery may
be ordered by the arbitrators according to procedures established by them.
A party has the right to the obtain a list of witnesses in examining copied
documents relevant to the arbitration. Witnesses are entitled to compensation
in the same manner as witnesses in superior court. O.C.G.A. § 9-9-9.
The arbitrators must render their award in writing and sign it. The award must be delivered to each party personally or by registered or certified mail, return receipt requested. The award must be made within the time fixed by the agreement or within 30 days following the close of the hearing if no provision is made in the agreement. A court may shorten or lengthen this time. The parties may extend in writing the time before or after its expiration. A party waives any objection to the award that is not made within the time required unless he notifies the arbitrators in writing of his objection prior to the delivery of the award to him. O.C.G.A. § 9-9-10.
Arbitrators are authorized to change the award if there is a miscalculation
or mistake, if they have awarded upon a manner not submitted to them, or
if the award is imperfect in a matter of form not affecting the merits
of the controversy. Application for a change in the award must be made
within 20 days after its delivery and must be served upon the other parties.
Objection to the change of the award by the arbitrators must be made within
10 days after service of the application for a change, and written notice
of this objection must be served on the other parties. The arbitrators
then have 30 days to rule on the objection. O.C.G.A. § 9-9-11.
The court must confirm the award within one year after its delivery.
O.C.G.A. § 9-9-12.
The court is authorized to vacate an award within three months after
delivery of the award for corruption, fraud, misconduct, partiality of
an arbitrator appointed as a neutral, overstepping of the authority of
the arbitrators, or failure to follow a procedure set out in the Georgia
Arbitration Code. Other grounds for vacating the award also exist. O.C.G.A.
§ 9-9-13. The award also may be modified by the court. O.C.G.A. §
9-9-14. Judgment may be obtained on the award, O.C.G.A. § 9-9-15,
and appeals are authorized, O.C.G.A. § 9-9-16.
Unless otherwise provided in the agreement to arbitrate, the arbitrator's
fees and expenses, not including counsel fees, incurred in the conduct
of the arbitration, shall be paid as provided in the award. O.C.G.A. §
9-9-17.
3. Federal Arbitration Act
(9 U.S.C. § 1)
There is also a procedure to enforce an arbitration agreement under
the Federal Arbitration Act. If a suit is brought on an issue referable
to arbitration under an arbitration agreement, a stay may be entered in
any court of the United States upon application of one of the parties.
9 U.S.C. § 3.
A party may compel arbitration under the Federal Arbitration Act by
petitioning the United States court having jurisdiction for an order to
compel arbitration. 9 U.S.C. § 4.
If the agreement makes provision for a method of naming or appointing
an arbitrator or arbitrators, such method shall be followed, but if no
method is provided or if one of the parties fails to use such method, or
for any reason there should be a lapse in the naming of an arbitrator,
then upon application the court shall designate and appoint an arbitrator
or arbitrators who shall act under the agreement. 9 U.S.C. § 5.
Under the Federal Arbitration Act, the arbitrators may summon in writing
any person to attend a hearing as witnesses and compel them to bring any
book, record, document, or paper which is deemed material as evidence in
the case. Fees for attendance shall be the same as fees for witnesses before
masters of the United States courts. A summons shall issue in the name
of the arbitrator or arbitrators and shall be directed to the person to
be served in the same manner as subpoenas to appear and testify are used
in court. A United States district court may be petitioned if to compel
attendance of such person or to punish such person for contempt of the
summons. 9 U.S.C. § 7.
If the parties have agreed that a judgment of the court shall be entered
upon the award made pursuant to the arbitration and so specify in court,
at any time within one year after the award a party may apply to confirm
the award and the court must grant a confirmation order unless the award
is vacated, modified, or corrected as prescribed by the Federal Arbitration
Act. 9 U.S.C. § 9.
An arbitration award may be vacated where an award was procured by corruption,
fraud, or undue means, where there was evident partiality or corruption
in the arbitrators, where the arbitrators were guilty of misconduct in
handling the hearing, where the arbitrators exceeded their powers or imperfectly
executed them. A court is authorized to direct the arbitrators to rehear
a matter, in its discretion. 9 U.S.C. § 10.
Where as miscalculation occurs or a mistake is made in description of
any person, thing, or property referred to in an award, or where the arbitrators
have awarded upon a manner not submitted to them, or where the award is
imperfect in matter of form not effecting the merits of the controversy,
a court is authorized to modify the award to correct the mistake. 9 U.S.C.
§ 11.
4. Compelling Surety to Arbitrate
Sureties have historically resisted being compelled to arbitrate disputes
between their principal and a claimant. The bonds issued by a surety usually
do not contain an express arbitration provision, but ordinarily do incorporate
by reference the construction contract which their principal has signed.
If that contract contains an arbitration provision, the modern trend finds
that the surety bond has incorporated the subcontract by reference and
that the arbitration provision in the contract also is incorporated by
reference into the bonded obligation.
Accordingly, if such an incorporation clause exists, the surety is required
to arbitrate. J.S. & H. Construction Company v. Richmond County
Hospital, 473 F.2d 212 (5th Cir. 1973); United Fidelity & Guaranty
Company v. West Point Construction Company, Inc., 837 F.2d 1507 (11th
Cir. 1988); Transamerica Premier Insurance Company v. Collins &
Company, General Contractors, Inc., 735 F.Supp. 1050 (N.D. Ga. 1990).
Language in the bond stating that "any suit" must be brought within
two years is not inconsistent with an agreement to arbitrate. Transamerica
Premier Insurance Company v. Collins & Company, General Contractors,
Inc., 735 F.Supp. 1050 (N.D. Ga. 1990).
5. Waiver of Arbitration
It is possible for a party to take actions which will be inconsistent
with proceeding under arbitration to resolve a dispute. If a party files
a complaint, pursues discovery, files motions in court, and in general
takes actions which completely disregard the arbitration provision, a court
may be authorized to find that the party waived its right to demand arbitration.
Where a party attempts to preserve these rights, however, arbitration will
not be waived. H.R.H. Prince LTC. Faisal M. Saud v. Batson-Cook Company,
161 Ga. App. 219, 291 S.E.2d 249 (1982).
6. Confirming or Overturning Arbitration Awards
As indicated earlier, an arbitration award must be confirmed within one year after it is returned by the arbitrators. A failure to confirm the award may result in waiving the award.
53. Mediation
Mediation is often a superior solution for the resolution of construction
disputes. Mediation may be conducted under the auspices of the American
Arbitration Association, which has formal rules and procedures for mediation.
Other companies offer this service and employ experienced construction
professionals, former judges, and others skilled in the mediation process.
Mediation is an effort to bring the parties together to a mutually agreeable
settlement. Mediation is nonbinding and the parties, not the mediator,
ultimately determine whether the case will settle.
Mediations should be conducted under a confidentiality agreement in
order to avoid prejudice to an arbitration or litigation of the claim subsequently.
The process works best if both parties have decision makers present
and participating in the mediation. It is usually helpful to have legal
counsel present to help organize the argument and effectively present each
party's position.
The process usually starts by an introductory statement of the position
of the parties. Then private sessions with the mediator are held in an
effort to determine whether common ground can be reached. A strong mediator
is often helpful. Errors in logic, faulty assumptions, and weak arguments
can be pointed out by the mediator.
Mediation is often successful in settling a case because it offers the decision makers for each side the first opportunity to hear their opponent's case unfiltered through the eyes and ears of their own personnel. Assessments of the strength and weakness of each side's case can be made. Mediation should occur only after thorough preparation of the case. Under these circumstances, mediation is surprisingly effective in achieving a resolution of construction claims.
54. Litigation
At the time suit is filed, a party must determine whether to demand
a jury trial or have its construction case tried before a judge. There
are advantages and disadvantages to both procedures.
With the judge trial, scheduling flexibility can be increased. More
interaction with the judge is possible than would be the case with a jury.
Accordingly, if the judge has questions, he can stop the proceedings, question
the expert, or request clarification from the attorney. This usually is
not possible with a jury trial.
Judges may have more familiarity with technical concepts and are, of
course, usually much more educated than the members of the jury.
Certain advantages also exist with the jury trial. A jury trial usually
occurs continuously until it is completed. The jury then retires and deliberates
until it reaches a verdict.
It is usually much more difficult to appeal from a judicial decision
than it is from the decision of a jury trial. Accordingly, an adverse decision
rendered by a judge may be difficult to reverse, while there may be more
possibility of reversing an adverse jury trial verdict.
The rules of evidence are strictly adhered to during a jury trial. This
offers the opportunity to exclude evidence which might be reviewed by a
judge "for what it's worth."
Juries are often viewed as being unsophisticated. Juries do, however,
have an excellent collective ability to determine who is lying and who
is telling the truth.
While court costs are charged in litigation, these costs usually are
much lower than fees for arbitration. Whoever prevails in the litigation
is awarded court costs virtually automatically.
There is no problem in litigation with compelling the attendance of
the parties and attorneys, since the judge can direct the attendance of
the attorneys at the trial and subpoenas are readily available to compel
the attendance of witnesses.
A trial occurs after a full discovery, including interrogatories, depositions,
requests for production of documents, and requests for admissions.
Discovery provides the opportunity to learn a great deal about the opponent's
case and for your opponent to learn a great deal about your case. This
is intended to facilitate settlement.
Litigation also can compel parties to participate in the dispute resolution process. A summons and complaint can be issued against any one subject to the jurisdiction and venue of the court. Third parties can be added under many circumstances.
With litigation, an appeal to a higher court is possible and may result
in a reversal of the trial court decision. If a case is appealed, a delay
of as much as a year or more may occur before the judgment is final.
55. Bankruptcy
Bankruptcy is a fact of life for construction contractors and owners
today. In order to make correct decisions, some understanding of the provisions
of the bankruptcy code is necessary.
A company can declare bankruptcy through Chapter 11 "reorganizations"
or Chapter 7 "liquidations."
A Chapter 11 reorganization is intended to permit the restructuring
of the company's debt with the idea that the company eventually will emerge
from bankruptcy.
Unfortunately, most Chapter 11 proceedings end up being converted into
Chapter 7 liquidations, where the company's assets are portioned out to
its creditors and the company dissolves.
While most construction contracts have provisions stating that the following
of bankruptcy is an event of default, these provisions usually are not
enforceable because they constitute impermissible "ipso facto" bankruptcy
clauses. In other words, the mere fact that a company declares bankruptcy
does not automatically mean that that company has defaulted under a construction
contract, even if the contract states to the contrary.
Accordingly, a company declaring bankruptcy may not be automatically
thrown off of a job or terminated. This can only occur if other events
of default such as stopping work, failing to pay suppliers, or failing
to maintain adequate progress in the work authorized the termination.
When a company declares bankruptcy, an "automatic stay" is entered which
if violated subjects the offender to severe penalties. Throwing the company
off the job, terminating the contract, seizing the company's tools and
equipment, or continuing to attempt to collect debts from the company all
constitute violations of the automatic stay.
The party may seek relief from the automatic stay by applying to the
bankruptcy court. At the same time, a party may apply to the bankruptcy
court requesting that the debtor assume remaining portions of the contract
and to provide "adequate assurance" of future performance. Such contract
assumed by the debtor becomes a "post-petition obligation" of the debtor
and may be treated like any other contract.
In a liquidation under Chapter 7, the main objective of the bankruptcy
is the distribution of the debtor's remaining assets to the creditors of
the debtor. In this situation, it is necessary for a claimant to file a
"proof of claim" in the bankruptcy court and to protect any "security interest"
that the party may have in the assets of the debtor's estate.
If a general contractor declares bankruptcy, it is still possible to pursue the general contractor's bonding company. It is also possible to follow lien, even if the party declaring bankruptcy is the owner. Perfection of rights already available to a party prior to the bankruptcy does not constitute a violation of the automatic stay, hence, a lien filing is permissible.
In a supplier's bankruptcy, a key question will be whether the contract
at issue is an "executory contract." Executory contracts are not defined
in the bankruptcy code but are generally considered to be contracts which
have yet to be performed by the debtor. The debtor may wait until its final
plan of reorganization is confirmed before the contract is accepted or
rejected. In this event, it is helpful to file a motion with the bankruptcy
court requiring the debtor to either assume or reject the supply contract.
In a Chapter 7 liquidation, executory contracts will be assumed or rejected
by the bankruptcy trustee within 60 days. If no action occurs, the contract
is deemed rejected and a proof of claim may be filed with the bankruptcy
court for damages.
Even if you do nothing further in a case, it is almost always appropriate to file a proof of claim. Unless the proof of claim is disputed by the debtor, your claim will ordinarily be accepted by the bankruptcy court. Secured creditors also have an opportunity to exercise their rights against secured property and to recover that property through the bankruptcy court.